View Case Filings for: 2025-00365


Case Number:2025-00365
Service Type:Electric
Filing Date:11/17/2025
Category:Regular
Utilities:

Kentucky Power Company


Electronic Case

ELECTRONIC APPLICATION OF KENTUCKY POWER COMPANY FOR (1) APPROVAL OF CONTINUATION OF ITS DEMAND-SIDE MANAGEMENT PROGRAMS; (2) AUTHORITY TO RECOVER COSTS AND NET LOST REVENUES, AND TO RECEIVE INCENTIVES ASSOCIATED WITH THE IMPLEMENTATION OF ITS DEMAND-SIDE MANAGEMENT PROGRAMS; (3) ACCEPTANCE OF ITS ANNUAL DSM STATUS REPORT; AND (4) ALL OTHER REQUIRED APPROVAL AND RELIEF









Case Filings
FilingDocuments
5/13/2026 11:04:02 AM

Kentucky Power Company’s Request to Submit Matter for Decision on the Record


Marilyn Michelle Caldwell Kentucky Power Company

KPCO_Request_to_Submit_for_Decision.pdf

KPCO’s Request to Submit Matter for Decision on the Record

5/11/2026 4:26:50 PM

Motion of Joint Intervenors for a Hearing


Byron L. Gary Joint Intervenors

2026-05-08-JI-HearingRequest.pdf

Motion of Joint Intervenors Appalachian Citizens’ Law Center and Mountain Association for a Hearing and the Establishment of a Procedural Schedule

4/30/2026 12:37:45 PM

Notice of Withdrawal of Counsel


Katie Glass Kentucky Power Company

4/29/2026 4:07:20 PM

Rebuttal Testimony of Stevi N. Cobern


Marilyn Michelle Caldwell Kentucky Power Company

02_KPCO_Cobern_Rebuttal_Testimony.pdf

KPCO's Rebuttal Testimony of Stevi N. Cobern

4/17/2026 4:38:28 PM

Attachment A to Responses of Joint Intervenors to Kentucky Power Company’s First Request for Information


Byron L. Gary Joint Intervenors

2026-00365_JI_Resp_to_KPC_1.1_Attachment_A.docx.pdf

Attachment A to Responses of Joint Intervenors Appalachian Citizens’ Law Center and Mountain Association to Kentucky Power Company’s First Request for Information

4/15/2026 5:11:52 PM

Responses of Joint Intervenors to First Requests for Information


Byron L. Gary Joint Intervenors

2026-00365_JI_Resp_to_KPC_1.1_Attachment_B.xlsx

Attachment B to Responses to Company

2026-04-15-JI-KPCO-DR1-Resp_Notarized.pdf

Responses of Joint Intervenors Appalachian Citizens’ Law Center and Mountain Association to Kentucky Power Company’s First Request for Information

2026-04-15-JI-Staff-DR1-Resp_Notarized.pdf

Responses of Joint Intervenors Appalachian Citizens’ Law Center and Mountain Association to Commission Staff’s First Request for Information

4/15/2026 5:06:47 PM

Corrected Exhibit SLS-2


Byron L. Gary Joint Intervenors

Exhibit_SLS-2.xlsx

Corrected Exhibit SLS-2 to Testimony of Stacy L. Sherwood on Behalf of Joint Intervenors Appalachian Citizens’ Law Center and Mountain Association to Kentucky Power Company

4/15/2026 11:39:20 AM

Kentucky Power Company’s responses to Commission Staff’s March 27, 2026 data requests


Marilyn Michelle Caldwell Kentucky Power Company

02_KPCO_R_KPSC_2026-04-15.pdf

KPCO’s responses to Commission Staff’s March 27, 2026 data requests

03_KPCO_R_KPSC_3_3_Attachment1.xlsx

KPCO_R_KPSC_3_3_Attachment1

04_KPCO_R_KPSC_3_6_Attachment1.xlsx

KPCO_R_KPSC_3_6_Attachment1

05_KPCO_R_KPSC_3_7_Attachment1.xlsx

KPCO_R_KPSC_3_7_Attachment1

4/1/2026 3:01:35 PM

Kentucky Power Company’s Data Requests to the Appalachian Citizens Law Center and Mountain Association


Marilyn Michelle Caldwell Kentucky Power Company

KPCO_Data_Requests_to_Joint_Intervenors.pdf

KPCO’s Data Requests to the Appalachian Citizens Law Center and Mountain Association

3/27/2026 3:32:12 PM

Data Request


3/27/2026 3:26:03 PM

Data Request


3/18/2026 9:01:41 PM

Testimony of Stacy L. Sherwood on Behalf of Joint Intervenors


Byron L. Gary Joint Intervenors

2026-03-18-JI-Testimony.pdf

Testimony of Stacy L. Sherwood on Behalf of Joint Intervenors Appalachian Citizens’ Law Center and Mountain Association to Kentucky Power Company

SLS-2_Testimony_Figures_and_Charts_Data.xlsx

Exhibit SLS-2 – Recalculation of D.S.M.C. Surcharge

3/4/2026 4:30:55 PM

Kentucky Power Company’s responses to Joint Intervenors’ February 18, 2026 data requests


Marilyn Michelle Caldwell Kentucky Power Company

KPCO_R_JI_2026-03-04.pdf

KPCO’s responses to Joint Intervenors’ February 18, 2026 data requests

3/4/2026 4:27:09 PM

Kentucky Power Company’s responses to Commission Staff’s February 16, 2026 data requests


Marilyn Michelle Caldwell Kentucky Power Company

02_KPCO_R_KPSC_2026-03-04.pdf

KPCO’s responses to Commission Staff’s February 16, 2026 data requests

03_KPCO_R_KPSC_2_4_Attachment2.xlsx

KPCO_R_KPSC_2_4_Attachment2

2/18/2026 7:03:21 PM

Supplemental Requests for Information of Joint Intervenors


Byron L. Gary Joint Intervenors

2026-02-18-JI-DR-2.pdf

Supplemental Requests for Information of Joint Intervenors Appalachian Citizens’ Law Center and Mountain Association to Kentucky Power Company

2/16/2026 4:19:24 PM

Data Request


2/4/2026 3:39:21 PM

Kentucky Power Company’s Responses to Joint Intervenors’ January 21, 2026 Data Requests


Marilyn Michelle Caldwell Kentucky Power Company

KPCO_R_JI_1_4_Attachment1.xlsx

KPCO_R_JI_1_4_Attachment1

KPCO_R_JI_2026-02-04.pdf

KPCO’s Responses to Joint Intervenors’ January 21, 2026 Data Requests

2/4/2026 3:35:44 PM

Kentucky Power Company’s Responses to Commission Staff’s January 15, 2026 Data Requests


Marilyn Michelle Caldwell Kentucky Power Company

KPCO_R_KPSC_1_4_Attachment1.xlsx

KPCO_R_KPSC_1_4_Attachment1

KPCO_R_KPSC_2026-02-04.pdf

KPCO’s Responses to Commission Staff’s January 15, 2026 Data Requests

1/21/2026 6:58:01 PM

Initial Requests for Information of Joint Intervenors


Byron L. Gary Joint Intervenors

2026-01-21-JI-DR-1.pdf

Initial Requests for Information of Joint Intervenors Appalachian Citizens’ Law Center and Mountain Association to Kentucky Power Company

1/20/2026 2:22:23 PM

Order Entered: 1. Joint Movants’ motion to intervene is granted. 2. Joint Intervenors are entitled to the full rights of a party and shall be served with the Commission’s Orders and with filed testimony, exhibits, pleadings, correspondence, and all other documents submitted by parties after the date of this Order. 3. Joint Intervenors shall comply with all provisions of the Commission’s regulations, 807 KAR 5:001, Section 8, related to the service and electronic filing of documents. 4. Joint Intervenors shall adhere to the procedural schedule set forth in the Commission’s December 8, 2025 Order and as amended by subsequent Orders. 5. Pursuant to 807 KAR 5:001, Section 8(9), within seven days of service of this Order, Joint Intervenors shall file a written statement with the Commission that: a. Certifies that it, or its agent, possesses the facilities to receive electronic transmissions; and b. Sets forth the electronic mail address to which all electronic notices and messages related to this proceeding shall be served.


1/15/2026 9:16:31 AM

Data Request


1/7/2026 8:32:21 PM

Joint Motion for Full Intervention as Joint Intervenors.


Byron L. Gary Joint Movants for Joint Intervention

2026-01-07-JI-mti.pdf

Joint Motion of Appalachian Citizens’ Law Center and Mountain Association for Full Intervention as Joint Intervenors.

12/8/2025 4:15:36 PM

Order Entered: 1. Kentucky Power’s proposed rates and tariff are suspended for five months from January 1, 2026, up to and including June 1, 2026. 2. Unless otherwise ordered by the Commission, the procedures set forth in 807 KAR 5:001, Section 8, related to service and electronic filing of papers shall be followed in this proceeding. 3. Pursuant to 807 KAR 5:001, Section 8(9), within seven days of the date of service of this Order, Kentucky Power shall file by electronic means a written statement that it waives any right to service of Commission Orders by United States mail and that it or its authorized agent possess the facilities to receive electronic submissions. 4. Unless a party granted leave to intervene states its objection to the use of electronic filing procedures in a motion for intervention, the party shall: a. Be deemed to have consented to the use of electronic filing procedures and the service of all papers, including Orders of the Commission, by electronic means; and b. Within seven days of the date of service of an order of the Commission granting intervention, file with the Commission a written statement that: (1) It or its authorized agent possesses the facilities to receive electronic transmissions; and (2) Sets forth the electronic mail address to which all electronic notices and messages related to this proceeding shall be served.


11/17/2025 5:39:15 PM

Kentucky Power Company’s Application


Marilyn Michelle Caldwell Kentucky Power Company

Exhibit_SNC-1.xls

Exhibit SNC-1

KPCO_DT_Cobern.pdf

Direct Testimony of Stevi N. Cobern

11/12/2025 9:32:56 AM

20251112_PSC Acknowledgment Letter.pdf


11/12/2025 9:30:30 AM

Kentucky Power Company Notice of Intent to File an Application for (1) Approval of Continuation of Its Demand-Side Management Programs; (2) Authority to Recover Costs and Net Lost Revenues, and to Receive Incentives Associated with the Implementation of it


20251112_Kentucky Power Company Notice of Intent and Election.pdf

Kentucky Power Company Notice of Intent and Election