View Case Filings for: 2022-00106
Service Type:Electric
Filing Date:2/28/2022
Category:Regular
Utilities:
Investigation of the Proposed Pole Attachment Tariffs of Rural Electric Cooperative Corporations
Electronic Case
Case Nature:
Investigation of the Proposed Pole Attachment Tariffs of Rural Electric Cooperative Corporations
Case Filings | |
---|---|
Filing | Documents |
12/28/2022 3:56:11 PM
Final Order Entered: 1. The RECCs proposed pole attachment tariff, (revised as discussed herein) is approved for service rendered on and after the date of this Order. 2. Within 30 days of the date of this Order, the each RECCs shall file with the Commission, using the Commission's electronic Tariff Filing System, their proposed tariffs (revised as discussed herein), setting out the rates and terms approved herein and reflecting that they were approved pursuant to this Order. 3. This case is closed and removed from the Commission’s docket. |
|
10/18/2022 8:09:48 PM
Reply Brief M Todd Osterloh Kentucky Broadband and Cable Association |
|
10/18/2022 3:50:55 PM
Response Brief of All Rural Electric Cooperative Corporations Edward T. Depp All Rural Electric Cooperative Corporations |
|
10/18/2022 3:48:28 PM
Response brief of EKPC L. Allyson Honaker East Kentucky Power Cooperative, Inc. |
|
10/18/2022 1:49:26 PM
ATT’s Response to Initial Brief in Case No. 2022-00106 Michaela Flewallen ATT Kentucky |
|
10/11/2022 5:05:47 PM
Initial Brief M Todd Osterloh Kentucky Broadband and Cable Association |
|
10/11/2022 3:51:12 PM
Initial Brief of the Rural Electric Cooperative Corporations Edward T. Depp All Rural Electric Cooperative Corporations |
|
9/23/2022 12:20:22 PM
Order Entered: 1. Any initial brief shall be filed no later than October 11, 2022. 2. Any response brief shall be filed no later than October 18, 2022. 3. Upon the filing of response briefs, the case shall stand submitted to the Commission for a decision. |
|
7/29/2022 9:37:54 PM
Notice of Substitution of Counsel L. Allyson Honaker Licking Valley RECC |
|
7/29/2022 9:36:27 PM
Notice of Substitution of Counsel L. Allyson Honaker East Kentucky Power Cooperative, Inc. |
|
7/18/2022 5:03:34 PM
Request for Briefing Schedule M Todd Osterloh Kentucky Broadband and Cable Association |
|
7/18/2022 4:09:03 PM
ATT Kentuckys Position Statement Regarding Hearing and Briefing Michaela Flewallen ATT Kentucky |
|
7/18/2022 3:42:14 PM
Joint Statement of Position on behalf of the Rural Electric Cooperative Corporations Edward T. Depp All Rural Electric Cooperative Corporations |
|
7/18/2022 10:29:41 AM
EAST KENTUCKY POWER COOPERATIVE, INC.’S NOTICE CONCERNING HEARING AND BRIEFING Chris Adams East Kentucky Power Cooperative, Inc. |
|
7/11/2022 4:15:56 PM
East Kentucky Power Cooperative, Inc. Rebuttal Testimony. Chris Adams East Kentucky Power Cooperative, Inc. |
|
7/11/2022 3:59:55 PM
Rebuttal Testimony of Sean Knowles on behalf of the Rural Electric Cooperative Corporations Edward T. Depp All Rural Electric Cooperative Corporations |
|
7/7/2022 7:50:40 PM
Response to RECCs RFI M Todd Osterloh Kentucky Broadband and Cable Association |
|
7/7/2022 7:48:35 PM
Response to EKPCs RFI M Todd Osterloh Kentucky Broadband and Cable Association |
|
7/7/2022 7:46:12 PM
Response to Commission Staffs RFI M Todd Osterloh Kentucky Broadband and Cable Association |
|
7/7/2022 3:16:39 PM
ATT Kentucky Response to Commission Staff Michaela Flewallen ATT Kentucky |
|
7/7/2022 3:11:02 PM
ATT Kentucky Response to East Kentucky Power Michaela Flewallen ATT Kentucky |
|
7/7/2022 2:54:33 PM
EKPCs Responses to Third Request for Information Chris Adams East Kentucky Power Cooperative, Inc. |
|
7/7/2022 11:54:08 AM
RECCs Joint Responses to Commission Staffs Third Request for Information Edward T. Depp All Rural Electric Cooperative Corporations |
|
6/23/2022 1:01:07 PM
First Request for Information to the KBCA Edward T. Depp All Rural Electric Cooperative Corporations |
|
6/23/2022 10:48:15 AM
EKPCs Information Requests to BellSouth Telecommunications, LLC d/b/a ATT Kentucky and the Kentucky Broadband and Cable Association. Chris Adams East Kentucky Power Cooperative, Inc. |
|
6/23/2022 9:52:45 AM
Data Request |
|
6/23/2022 9:35:32 AM
Data Request |
|
6/23/2022 9:31:30 AM
Data Request |
|
6/9/2022 5:06:03 PM
ATT Kentucky Testimony of Dan Rhinehart Michaela Flewallen ATT Kentucky |
|
6/9/2022 4:54:40 PM
Testimony M Todd Osterloh Kentucky Broadband and Cable Association |
|
6/3/2022 3:39:46 PM
Order Entered: 1. KBCA’s motion is denied to the extent it sought to amend the procedural schedule to establish deadlines for filing legal briefs with intervenor and rebuttal testimony. 2. Parties shall jointly or separately state their positions, if any, regarding briefing, including the order and timing of briefing, on or before July 18, 2022. |
|
6/2/2022 3:51:35 PM
RECCs Motion for Confidential Treatment Edward T. Depp All Rural Electric Cooperative Corporations |
|
6/2/2022 3:33:58 PM
Responses to the KBCAs Supplemental Requests for Information Edward T. Depp Taylor County R.E.C.C. |
|
6/2/2022 3:31:20 PM
Responses to Commission Staffs Second Requests for Information Edward T. Depp Taylor County R.E.C.C. |
|
6/2/2022 3:28:59 PM
Responses to the KBCAs Supplemental Requests for Information Edward T. Depp South Kentucky R.E.C.C. |
|
6/2/2022 3:26:42 PM
Responses to Commission Staffs Second Requests for Information Edward T. Depp South Kentucky R.E.C.C. |
|
6/2/2022 3:24:41 PM
Cover Letter to Ms. Linda Bridwell, P.E., Motion for Confidential Treatment for the information and documents tendered by EKPC in Response to Request No. 5 and Responses to Commission Staffs Second Request for Information dated May 19, 2022. Chris Adams East Kentucky Power Cooperative, Inc. |
|
6/2/2022 3:23:26 PM
Responses to the KBCAs Supplemental Requests for Information Edward T. Depp Shelby Energy Cooperative, Inc. |
|
6/2/2022 3:20:18 PM
Responses to Commission Staffs Second Requests for Information Edward T. Depp Shelby Energy Cooperative, Inc. |
|
6/2/2022 3:17:10 PM
Responses to the KBCAs Supplemental Requests for Information Edward T. Depp Salt River Electric Cooperative Corp. |
|
6/2/2022 3:13:36 PM
Responses to Commission Staffs Second Requests for Information Edward T. Depp Salt River Electric Cooperative Corp. |
|
6/2/2022 3:10:51 PM
Responses to the KBCAs Supplemental Requests for Information Edward T. Depp Owen Electric Cooperative, Inc. |
|
6/2/2022 3:08:44 PM
Responses to Commission Staffs Second Requests for Information Edward T. Depp Owen Electric Cooperative, Inc. |
|
6/2/2022 3:04:20 PM
Responses to the KBCAs Supplemental Requests for Information Edward T. Depp Nolin R.E.C.C. |
|
6/2/2022 3:01:51 PM
Responses to Commission Staffs Second Requests for Information Edward T. Depp Nolin R.E.C.C. |
|
6/2/2022 2:58:53 PM
Responses to the KBCAs Supplemental Requests for Information Edward T. Depp Licking Valley R.E.C.C. |
|
6/2/2022 2:56:16 PM
Responses to Commission Staffs Second Requests for Information Edward T. Depp Licking Valley R.E.C.C. |
|
6/2/2022 2:41:27 PM
Responses to the KBCAs Supplemental Requests for Information Edward T. Depp Meade County R.E.C.C. |
|
6/2/2022 2:38:40 PM
Responses to Commission Staffs Second Requests for Information Edward T. Depp Meade County R.E.C.C. |
|
6/2/2022 2:35:06 PM
Responses to the KBCAs Supplemental Requests for Information Edward T. Depp Kenergy Corp. |
|
6/2/2022 2:32:01 PM
Responses to Commission Staffs Second Requests for Information Edward T. Depp Kenergy Corp. |
|
6/2/2022 2:25:01 PM
Responses to the KBCAs Supplemental Requests for Information Edward T. Depp Jackson Purchase Energy Corporation |
|
6/2/2022 2:22:00 PM
Responses to Commission Staffs Second Requests for Information Edward T. Depp Jackson Purchase Energy Corporation |
|
6/2/2022 2:16:19 PM
Responses to the KBCAs Supplemental Requests for Information Edward T. Depp Jackson Energy Cooperative Corporation |
|
6/2/2022 2:05:28 PM
Responses to Commission Staffs Second Requests for Information Edward T. Depp Jackson Energy Cooperative Corporation |
|
6/2/2022 1:59:59 PM
Responses to the KBCAs Supplemental Requests for Information Edward T. Depp Inter-County Energy Cooperative Corporation |
|
6/2/2022 1:57:14 PM
Responses to Commission Staffs Second Requests for Information Edward T. Depp Inter-County Energy Cooperative Corporation |
|
6/2/2022 1:53:28 PM
Responses to the KBCAs Supplemental Requests for Information Edward T. Depp Grayson R.E.C.C. |
|
6/2/2022 1:51:05 PM
Responses to Commission Staffs Second Requests for Information Edward T. Depp Grayson R.E.C.C. |
|
6/2/2022 1:45:06 PM
Responses to the KBCAs Supplemental Requests for Information Edward T. Depp Fleming-Mason Energy Cooperative, Inc. |
|
6/2/2022 1:42:26 PM
Responses to Commission Staffs Second Requests for Information Edward T. Depp Fleming-Mason Energy Cooperative, Inc. |
|
6/2/2022 1:39:16 PM
Responses to the KBCAs Supplemental Requests for Information Edward T. Depp Farmers R.E.C.C. |
|
6/2/2022 1:37:06 PM
Responses to Commission Staffs Second Requests for Information Edward T. Depp Farmers R.E.C.C. |
|
6/2/2022 1:34:07 PM
Responses to the KBCAs Supplemental Requests for Information Edward T. Depp Cumberland Valley Electric, Inc. |
|
6/2/2022 1:32:11 PM
Responses to Commission Staffs Second Requests for Information Edward T. Depp Cumberland Valley Electric, Inc. |
|
6/2/2022 1:29:07 PM
Responses to the KBCAs Supplemental Requests for Information Edward T. Depp Clark Energy Cooperative, Inc. |
|
6/2/2022 1:26:36 PM
Responses to Commission Staffs Second Requests for Information Edward T. Depp Clark Energy Cooperative, Inc. |
|
6/2/2022 1:23:27 PM
Responses to the KBCAs Supplemental Requests for Information Edward T. Depp Blue Grass Energy Cooperative Corp. |
|
6/2/2022 1:21:19 PM
Responses to Commission Staffs Second Requests for Information Edward T. Depp Blue Grass Energy Cooperative Corp. |
|
6/2/2022 1:18:41 PM
Responses to KBCAs Supplemental Requests for Information Edward T. Depp Big Sandy R.E.C.C. |
|
6/2/2022 1:16:19 PM
Responses to Commission Staffs Second Requests for Information Edward T. Depp Big Sandy R.E.C.C. |
|
6/2/2022 1:12:54 PM
Responses to the KBCAs Supplemental Requests for Information Edward T. Depp Big Rivers Electric Corporation |
|
6/2/2022 1:10:03 PM
Responses to Commission Staffs Second Requests for Information Edward T. Depp Big Rivers Electric Corporation |
|
5/19/2022 6:02:38 PM
Supplemental Requests for Information M. Todd Osterloh Kentucky Broadband and Cable Association |
|
5/19/2022 4:50:53 PM
Response to KBCAs Motion for Clarification Edward T. Depp All Rural Electric Cooperative Corporations |
|
5/19/2022 1:51:56 PM
Data Request |
|
5/13/2022 10:58:06 AM
Order Entered: Paul Werner and Hannah Wigger are admitted pro hac vice for the purpose of representing KBCA in association with James W. Gardner in the above-styled proceeding, provided that James W. Gardner or another member of the Kentucky Bar Association acts as co-counsel and is present at all proceedings before this Commission. |
|
5/12/2022 10:03:12 PM
Motion for Clarification M Todd Osterloh Kentucky Broadband and Cable Association |
|
5/12/2022 1:04:20 PM
Supplemental Filing for Responses to Commission Staffs First Requests for Information. Edward T. Depp Shelby Energy Cooperative, Inc. |
|
5/6/2022 2:52:44 PM
Supplemental Filing for Responses to Commission Staffs First Request for Information Edward T. Depp Blue Grass Energy Cooperative Corp. |
|
5/6/2022 9:59:24 AM
Supplemental Filing for Responses to Commission Staffs First Requests for Information Edward T. Depp Owen Electric Cooperative, Inc. |
|
5/5/2022 5:34:31 PM
Responses to the KBCAs Initial Requests for Information Edward T. Depp Big Rivers Electric Corporation |
|
5/5/2022 5:32:17 PM
Responses to the Commission Staffs First Requests for Information Edward T. Depp Big Rivers Electric Corporation |
|
5/5/2022 5:25:07 PM
Responses to the KBCAs Initial Requests for Information Edward T. Depp Taylor County R.E.C.C. |
|
5/5/2022 5:23:23 PM
Responses to the Commission Staffs First Requests for Information Edward T. Depp Taylor County R.E.C.C. |
|
5/5/2022 5:20:39 PM
Responses to the KBCAs Initial Requests for Information Edward T. Depp South Kentucky R.E.C.C. |
|
5/5/2022 5:18:23 PM
Responses to the Commission Staffs First Requests for Information Edward T. Depp South Kentucky R.E.C.C. |
|
5/5/2022 5:15:20 PM
Responses to the KBCAs Initial Requests for Information Edward T. Depp Shelby Energy Cooperative, Inc. |
|
5/5/2022 5:13:28 PM
Responses to the Commission Staffs First Requests for Information Edward T. Depp Shelby Energy Cooperative, Inc. |
|
5/5/2022 5:10:02 PM
Responses to the KBCAs Initial Requests for Information Edward T. Depp Salt River Electric Cooperative Corp. |
|
5/5/2022 5:07:52 PM
Responses to the Commission Staffs First Requests for Information Edward T. Depp Salt River Electric Cooperative Corp. |
|
5/5/2022 5:04:10 PM
Responses to the KBCAs Initial Requests for Information Edward T. Depp Owen Electric Cooperative, Inc. |
|
5/5/2022 4:55:11 PM
Responses to the Commission Staffs First Requests for Information Edward T. Depp Owen Electric Cooperative, Inc. |
|
5/5/2022 4:49:31 PM
Responses to the KBCAs Initial Requests for Information Edward T. Depp Nolin R.E.C.C. |
|
5/5/2022 4:47:42 PM
Responses to the Commission Staffs First Requests for Information Edward T. Depp Nolin R.E.C.C. |
|
5/5/2022 4:40:42 PM
Responses to the KBCAs Initial Requests for Information Edward T. Depp Meade County R.E.C.C. |
|
5/5/2022 4:38:19 PM
Responses to the Commission Staffs First Requests for Information Edward T. Depp Meade County R.E.C.C. |
|
5/5/2022 4:35:19 PM
Responses to the KBCAs Initial Requests for Information Edward T. Depp Licking Valley R.E.C.C. |
|
5/5/2022 4:33:31 PM
Responses to the Commission Staffs First Requests for Information Edward T. Depp Licking Valley R.E.C.C. |
|
5/5/2022 4:26:58 PM
Responses to the KBCAs Initial Requests for Information Edward T. Depp Kenergy Corp. |
|
5/5/2022 4:25:17 PM
Responses to the Commission Staffs First Requests for Information Edward T. Depp Kenergy Corp. |
|
5/5/2022 4:22:35 PM
Responses to the KBCAs Initial Requests for Information ed Jackson Purchase Energy Corporation |
|
5/5/2022 4:20:49 PM
Responses to the Commission Staffs First Requests for Information Edward T. Depp Jackson Purchase Energy Corporation |
|
5/5/2022 4:15:37 PM
Responses to the KBCAs Initial Requests for Information Edward T. Depp Jackson Energy Cooperative Corporation |
|
5/5/2022 4:13:53 PM
Responses to the Commission Staffs First Requests for Information Edward T. Depp Jackson Energy Cooperative Corporation |
|
5/5/2022 4:08:15 PM
Responses to the KBCAs Initial Requests for Information Edward T. Depp Inter-County Energy Cooperative Corporation |
|
5/5/2022 4:06:32 PM
Responses to the Commission Staffs First Requests Edward T. Depp Inter-County Energy Cooperative Corporation |
|
5/5/2022 4:02:11 PM
Responses to the KBCAs Initial Requests for Information Edward T. Depp Grayson R.E.C.C. |
|
5/5/2022 4:00:01 PM
Responses to the Commission Staffs First Requests for Information Edward T. Depp Grayson R.E.C.C. |
|
5/5/2022 3:55:10 PM
Responses to the KBCAs Initial Requests for Information Edward T. Depp Fleming-Mason Energy Cooperative, Inc. |
|
5/5/2022 3:52:31 PM
Responses to the Commission Staffs First Requests for Information Edward T. Depp Fleming-Mason Energy Cooperative, Inc. |
|
5/5/2022 3:49:08 PM
Responses to the KBCAs Initial Requests for Information Edward T. Depp Farmers R.E.C.C. |
|
5/5/2022 3:46:36 PM
Responses to the Commission Staffs First Requests for Informaiton Edward T. Depp Farmers R.E.C.C. |
|
5/5/2022 3:27:07 PM
Responses to the KBCAs Initial Requests for Information Edward T. Depp Cumberland Valley Electric, Inc. |
|
5/5/2022 3:25:01 PM
Responses to the Commission Staffs First Requests for Information Edward T. Depp Cumberland Valley Electric, Inc. |
|
5/5/2022 3:20:52 PM
Responses to the KBCAs Initial Requests for Information Edward T. Depp Clark Energy Cooperative, Inc. |
|
5/5/2022 3:16:56 PM
Responses to Commission Staffs First Requests for Information Edward T. Depp Clark Energy Cooperative, Inc. |
|
5/5/2022 3:11:36 PM
Responses to the KBCAs Initial Requests for Information Edward T. Depp Blue Grass Energy Cooperative Corp. |
|
5/5/2022 3:09:30 PM
Responses to Commissions Staffs First Requests for Information Edward T. Depp Blue Grass Energy Cooperative Corp. |
|
5/5/2022 3:05:32 PM
Responses to the KBCAs Initial Requests for Information Edward T. Depp Big Sandy R.E.C.C. |
|
5/5/2022 3:01:27 PM
Responses to Commission Staffs First Requests for Information Edward T. Depp Big Sandy R.E.C.C. |
|
5/5/2022 2:14:16 PM
EKPCs responses to PSCs data request 1 dated 4-22-22. Chris Adams East Kentucky Power Cooperative |
|
4/21/2022 6:27:10 PM
RFI to RECCs M Todd Osterloh Kentucky Broadband and Cable Association |
|
4/21/2022 2:12:10 PM
Data Request |
|
4/14/2022 2:19:53 PM
Rural Electric Cooperative Corporations Response to KBCAs and ATTs Objections Edward T. Depp All Rural Electric Cooperative Corporations |
|
4/8/2022 12:30:51 PM
Motion to Admit Pro Hac Vice M. Todd Osterloh Kentucky Broadband and Cable Association |
|
4/6/2022 10:30:26 AM
Written Statement Pursuant to Commissions Order James Crawford Owen Electric Cooperative, Inc. |
|
4/5/2022 4:34:13 PM
ATT Kentucky Entry of Appearance Michaela Flewallen ATT Kentucky |
|
4/5/2022 3:08:33 PM
Entry of Appearance and Electronic Filings Certification Mark David Goss Licking Valley RECC |
|
4/5/2022 1:51:22 PM
Entry of Appearance and Electronic Filing Certification Mark David Goss South Kentucky RECC |
|
4/5/2022 1:45:41 PM
Entry of Appearance M. Todd Osterloh Kentucky Broadband and Cable Association |
|
4/5/2022 11:55:15 AM
Notice of Entry of Appearance April Renner Jackson Energy Cooperative Corporation |
|
4/5/2022 9:55:13 AM
Entry of Appearance DAVID T ROYSE Blue Grass Energy |
|
4/4/2022 10:07:31 AM
Entry of Appearance Earl Rogers Fleming-Mason Energy Cooperative, Inc. |
|
4/1/2022 4:56:03 PM
Notice of Entry of Appearance and Electronic Certification L. Allyson Honaker East Kentucky Power Cooperative, Inc. |
|
4/1/2022 4:55:54 PM
Entry of Appearance Co-Counsel for Owen Electric Cooperative, Inc. James M. Crawford Owen Electric Cooperative, Inc. |
|
4/1/2022 4:40:43 PM
Entry of Appearance Derrick Willis Grayson Rural Electric Cooperative Corporation |
|
4/1/2022 2:35:13 PM
Notice of Appearance Edward T. Depp All Rural Electric Cooperative Corporations |
|
3/30/2022 2:19:02 PM
Order Entered: 1. This proceeding is established to investigate the reasonableness of the proposed tariffs. 2. The proposed tariffs of Big Rivers Electric Corporation, Big Sandy R.E.C.C., Blue Grass Energy Cooperative Corp., Clark Energy Cooperative, Inc., Cumberland Valley Electric, Inc., Farmers R.E.C.C., Fleming-Mason Energy Cooperative, Inc., Grayson R.E.C.C., Inter-County Energy Cooperative Corporation, Jackson Energy Cooperative Corporation, Jackson Purchase Energy Corporation, Kenergy Corp., Licking Valley R.E.C.C., Meade County R.E.C.C., Nolin R.E.C.C., Owen Electric Cooperative, Inc., Salt River Electric Cooperative Corp., Shelby Energy Cooperative, Inc., South Kentucky R.E.C.C., Taylor County R.E.C.C., and EKPC are suspended for five months from March 31, 2022, up to and including August 31, 2022. 3. AT&T Kentucky and KBCA are made parties to this proceeding. 4. AT&T Kentucky’s and KBCA’s objections and comments filed in Case No. 2022-00064 are incorporated by reference into the records of this proceeding. |
|
3/29/2022 3:44:56 PM
Big Rivers Electric Corporation Tariff Filing |
|
3/29/2022 3:43:18 PM
Big Sandy RECC Tariff Filing |
|
3/29/2022 3:41:05 PM
Blue Grass Energy Cooperative Corp. Tariff Filing |
|
3/29/2022 3:38:25 PM
Clark Energy Cooperative, Inc. Tariff Filing |
|
3/29/2022 3:36:41 PM
Cumberland Valley Electric, Inc. Tariff Filing |
|
3/29/2022 3:33:35 PM
East Kentucky Power Cooperative, Inc. Tariff Filing |
|
3/29/2022 3:32:31 PM
Farmers RECC Tariff Filing |
|
3/29/2022 3:31:06 PM
Fleming-Mason Energy Cooperative, Inc. Tariff Filing |
|
3/29/2022 3:29:37 PM
Grayson R.E.C.C. Tariff Filing |
|
3/29/2022 3:27:50 PM
Inter-County Energy Cooperative Corporation Tariff Filing |
|
3/29/2022 3:23:59 PM
Jackson Energy Cooperative Corporation Tariff Filing |
|
3/29/2022 3:21:07 PM
Jackson Purchase Energy Corporation Tariff Filing |
|
3/29/2022 3:18:31 PM
Kenergy Corp. Tariff Filing |
|
3/29/2022 3:15:38 PM
Licking Valley R.E.C.C. Tariff Filing |
|
3/29/2022 3:12:40 PM
Meade County R.E.C.C. Tariff Filing |
|
3/29/2022 3:09:33 PM
Nolin R.E.C.C. Tariff Filing |
|
3/29/2022 3:07:24 PM
Owen Electric Cooperative, Inc. Tariff Filing |
|
3/29/2022 3:04:02 PM
Salt River Electric Cooperative Corp. Tariff Filing |
|
3/29/2022 3:00:23 PM
Shelby Energy Cooperative, Inc. Tariff Filing |
|
3/29/2022 2:58:20 PM
South Kentucky R.E.C.C. Tariff Filing |
|
3/29/2022 2:56:18 PM
Taylor County R.E.C.C. Tariff Filing |