View Case Filings for: 2023-00183
Service Type:Water
Filing Date:7/6/2023
Category:Regular
Utilities:
North Manchester Water Association, Inc.
Electronic Case
Case Nature:
ELECTRONIC APPLICATION OF NORTH MANCHESTER WATER ASSOCIATION, INC. FOR AN ALTERNATIVE RATE ADJUSTMENT
Case Filings | |
---|---|
Filing | Documents |
11/29/2023 6:17:03 PM
Response to Third Request for Information M Todd Osterloh North Manchester Water Association |
|
11/21/2023 10:29:05 AM
20231121_PSC Letter Filing Field Review Memo into the Record.pdf |
|
11/15/2023 10:36:25 AM
Data Request |
|
10/30/2023 8:04:41 PM
Response to Second Request for Information M Todd Osterloh North Manchester Water Association |
|
10/27/2023 6:43:57 PM
Motion for Extension of Time M Todd Osterloh North Manchester Water Association |
|
10/13/2023 3:25:08 PM
Data Request |
|
10/10/2023 8:12:40 AM
20231010_PSC Letter Filing IC Memo into the Record.pdf |
|
10/9/2023 3:01:29 PM
Order Entered: 1. North Manchester Water shall make Ted Woods, Rose Lewis, Bill Gray, and Mike Maggard available to Commission Staff during the November 8, 2023 field visit. 2. Within seven days of the date of service of this Order, North Manchester Water shall file a list of any other North Manchester officers, agents, and employees who North Manchester Water will make available to Commission Staff during the November 8, 2023 field visit. 3. North Manchester Water shall make the records identified in this Order available to Commission Staff during the November 8, 2023 field visit. |
|
10/6/2023 2:24:50 PM
Order Entered: 1. The procedural scheduled established on July 31, 2023, and amended on September 12, 2023, is amended. 2. A Field Review shall be conducted on November 8, 2023. 3. The amended procedural schedule set forth in the Appendix of this Order shall be followed. 4. All provisions of the Commission’s July 31, 2023 Order that are not in conflict with this Order shall remain in effect. |
|
9/25/2023 4:08:53 PM
Notice of Informal Conference |
|
9/25/2023 4:05:42 PM
Order Entered: 1. North Manchester Water’s petition for confidential treatment is granted. 2. The designated material granted confidential treatment by this Order shall not be placed in the public record or made available for public inspection for an indefinite period or until further Order of this Commission. 3. Use of the designated material granted confidential treatment by this Order in any Commission proceeding shall comply with 807 KAR 5:001, Section 13(9). 4. North Manchester Water shall inform the Commission if the designated material granted confidential treatment by this Order becomes publicly available or no longer qualifies for confidential treatment. 5. If a nonparty to this proceeding requests to inspect the material granted confidential treatment by this Order and the period during which the material has been granted confidential treatment has not expired, North Manchester Water shall have 30 days from receipt of written notice of the request to demonstrate that the material still falls within the exclusions from disclosure requirements established in KRS 61.878. If North Manchester Water is unable to make such demonstration, the requested material shall be made available for inspection. Otherwise, the Commission shall deny the request for inspection. |
|
9/20/2023 3:03:45 PM
Notice of Filing - Excel for PSC DR 1-4 M Todd Osterloh North Manchester Water Association |
|
9/20/2023 12:36:22 PM
Redacted Response to Request for Information M Todd Osterloh North Manchester Water Association |
|
9/15/2023 6:22:38 PM
Response to Request for Information M Todd Osterloh North Manchester Water Association |
|
9/12/2023 1:48:55 PM
Order Entered: 1. North Manchester Water’s motion for additional time is granted. 2. North Manchester Water shall file its responses to Staff’s First Request no later than September 15, 2023. 3. The Commission does not look favorably upon motions for continuance. Accordingly, future motions for extensions of time with respect to the amended procedural schedule shall be made in writing and will be granted only upon a showing of good cause. 4. The amended procedural schedule set forth in the Appendix to this Order shall be followed. 5. All provisions of the Commission’s July 31, 2023 Order that are not in conflict with this Order shall remain in effect. |
|
8/30/2023 4:45:53 PM
Request for Extension of Time M. Todd Osterloh North Manchester Water Association |
|
8/1/2023 1:21:13 PM
Notice of Publication M Todd Osterloh North Manchester Water Association |
|
7/31/2023 12:41:04 PM
Order Entered: 1. The procedural schedule set forth in Appendix A to this Order shall be followed. 2. On or before the date set forth in the procedural schedule, North Manchester Water shall file its responses to the Commission Staff’s request for information, attached to this Order as Appendix B. 3. North Manchester Water shall respond to any additional requests for information propounded by Commission Staff as provided in those requests. 4. No later than the date set forth in the procedural schedule, Commission Staff shall file with the Commission and serve upon all parties of record a written report (Commission Staff’s Report) containing its findings and recommendations regarding North Manchester Water’s requested rate adjustment. |
|
7/7/2023 12:00:20 PM
20230707_PSC Deficiency Cured Letter.pdf |
|
7/6/2023 2:23:53 PM
Response to Deficiency Letter M Todd Osterloh North Manchester Water Association |
|
6/26/2023 4:22:33 PM
20230626_PSC Deficiency Letter.pdf |
|
6/22/2023 3:53:57 PM
Response to Deficiency Letter M Todd Osterloh North Manchester Water Association |
|
6/12/2023 3:05:54 PM
20230612_PSC Deficiency Letter.pdf |
|
6/1/2023 3:46:31 PM
Application M Todd Osterloh North Manchester Water Association |
|
5/23/2023 3:16:55 PM
20230523_PSC Acknowledgment Letter.pdf |
|
5/23/2023
North Manchester Water Association, Inc. Notice of Intent to File an Application for an Alternative Rate Adjustment Using Electronic Filing Procedures |