View Case Filings for: 2024-00016
Service Type:Electric
Filing Date:1/31/2024
Category:Regular
Utilities:
Kentucky Power Company
Electronic Case
Case Nature:
ELECTRONIC APPLICATION OF KENTUCKY POWER COMPANY FOR: (1) APPROVAL OF THE ROCKPORT OFFSET TRUE-UP AMOUNT; (2) APPROVAL TO COLLECT THE ROCKPORT OFFSET TRUE-UP THROUGH TARIFF PURCHASE POWER ADJUSTMENT; AND (3) ALL OTHER REQUIRED APPROVALS AND RELIEF
Case Filings | |
---|---|
Filing | Documents |
12/20/2024 10:07:12 AM
Final Order Entered: 1. Kentucky Power’s motion, on behalf of all the parties in this matter, for reconsideration is granted. 2. The full amount$18,045,496 of the Rockport Offset True-Up shall be recovered through the Tariff P.P.A. over 19 months. 3. Recognizing that at least one billing period has passed since Exhibit 1 was created, Kentucky Power shall bill the Rockport Offset True-Up recovery amount through the Tariff P.P.A. as proposed in Scenario B of its motion. 4. Upon full recovery of the amount, Kentucky Power shall file notice in this case and include confirmation that Kentucky Power has stopped including the recovery in the Tariff P.P.A. referencing this case number in post-case correspondence. 5. The remainder of the November 27, 2024 Order not in conflict with this Order remains in effect. 6. This case is closed and removed from the Commission’s docket. |
|
12/11/2024 4:11:24 PM
Joint Motion For Limited Rehearing Marilyn Michelle Caldwell Kentucky Power Company |
|
12/4/2024 4:25:36 PM
Order Entered: 1. Kentucky Power’s motion for an IC is granted. 2. An IC is scheduled on December 5, 2024, at 9 a.m. Eastern Standard Time. 3. Commission Staff will contact participants by electronic mail to provide details for joining the conference by video link. |
|
11/27/2024 11:46:10 AM
Final Order Entered: 1. The Tariff P.P.A. rates proposed by Kentucky Power are denied. 2. The Tariff P.P.A. rates, as set forth in the Appendix to this Order, are approved as fair, just and reasonable rates for Kentucky Power, and these rates are approved for service rendered from March 2, 2024, to September 27, 2024. 3. Kentucky Power shall refund its customers for the actual overcharge for rates for service rendered between March 2, 2024, and September 27, 2024. 4. Kentucky Power shall provide a single bill credit, when feasible, for the amount. 5. Kentucky Power shall provide notice to the Commission, in this case, once the refund to all entitled customers has been accomplished. 6. Within 20 days of the date of service of this Order, Kentucky Power shall file with this Commission, using the Commission’s electronic Tariff Filing System, revised tariff sheets setting out the rates approved herein and reflecting that they were approved pursuant to this Order and effective from March 2, 2024, to September 27, 2024. 7. This case is closed and removed from the Commission’s docket. |
|
8/16/2024 3:14:48 PM
Kentucky Power Company’s Motion to Place Proposed Rates Into Effect Subject to Refund Pursuant to KRS 278.190(2) Marilyn Michelle Caldwell Kentucky Power Company |
|
4/24/2024 4:06:52 PM
Kentucky Industrial Utility Customers (KIUC) Notice Regarding Hearing Michael L. Kurtz Kentucky Industrial Utility Customers (KIUC) |
|
4/23/2024 9:43:38 AM
Notice Regarding Hearing J. Michael West Office of the Attorney General |
|
4/3/2024 2:14:10 PM
Notice That Kentucky Power Company Will Not File Requests for Information Or Rebuttal Testimony And Request To Submit Matter For Decision On The Record Marilyn Michelle Caldwell Kentucky Power Company |
|
3/4/2024 2:07:32 PM
Kentucky Power Company’s Responses to Commission Staff’s February 19, 2024 Data Requests Marilyn Michelle Caldwell Kentucky Power Company |
|
2/28/2024 4:30:30 PM
Kentucky Power Company’s 2023 Financial Statements and Supplemental Exhibits for Heather M. Whitney and Lerah M. Kahn Marilyn Michelle Caldwell Kentucky Power Company |
|
2/23/2024 12:53:41 PM
Kentucky Industrial Utility Customers (KIUC) Written Statement of Mail Waiver Michael L. Kurtz Kentucky Industrial Utility Customers (KIUC) |
|
2/23/2024 12:15:02 PM
Order Entered: 1. KIUC’s motion to intervene is granted. 2. KIUC is entitled to the full rights of a party and shall be served with the Commission’s Orders and with filed testimony, exhibits, pleadings, correspondence, and all other documents submitted by parties after the date of this Order. 3. KIUC shall comply with all provisions of the Commission’s regulations, 807 KAR 5:001, Section 8, related to the service and electronic filing of documents.4. KIUC shall adhere to the procedural schedule set forth in the Commission’s February 12, 2024 Order and as amended by subsequent Orders. 5. Pursuant to 807 KAR 5:001, Section 8(9), within seven days of service of this Order, KIUC shall file a written statement with the Commission that: a. Certifies that it, or its agent, possesses the facilities to receive electronic transmissions; and b. Sets forth the electronic mail address to which all electronic notices and messages related to this proceeding shall be served. |
|
2/19/2024 3:03:47 PM
Data Request |
|
2/15/2024 3:00:23 PM
Order Entered: 1. The Attorney General’s motion to intervene is granted. 2. The Attorney General is entitled to the full rights of a party and shall be served with the Commission’s Orders and with filed testimony, exhibits, pleadings, correspondence, and all other documents submitted by parties after the date of this Order. 3. The Attorney General shall comply with all provisions of the Commission’s regulations, 807 KAR 5:001, Section 8, related to the service and electronic filing of documents. 4. Pursuant to 807 KAR 5:001, Section 8(9), within seven days of service of this Order, the Attorney General shall file a written statement with the Commission that: a. Certifies that it, or its agent, possesses the facilities to receive electronic transmissions; and b. Sets forth the electronic mail address to which all electronic notices and messages related to this proceeding shall be served. |
|
2/15/2024 11:42:30 AM
Kentucky Power Company’s Notice of Intent to Place Proposed Rates Into Effect Subject to Refund Pursuant to KRS 278.190(2) Marilyn Michelle Caldwell Kentucky Power Company |
|
2/15/2024 11:29:35 AM
Notice of Entry of Appearance of Counsel and Written Statement of Kentucky Power Company Marilyn Michelle Caldwell Kentucky Power Company |
|
2/14/2024 12:25:13 PM
Kentucky Industrial Utility Customers (KIUC) Motion to Intervene Michael L. Kurtz Kentucky Industrial Utility Customers (KIUC) |
|
2/12/2024 1:53:55 PM
Order Entered: 1. Kentucky Power’s proposed rate is suspended for one day, to be effective March 2, 2024, subject to refund. 2. Kentucky Power shall maintain its records in such a manner as will allow it, the Commission, or any customer to determine the amounts to be refunded, and to whom, in the event a refund is ordered upon a final resolution of this matter. 3. Within 20 days of the date of this Order, Kentucky Power shall file with this Commission, using the Commission’s electronic Tariff Filing System, revised tariff sheets setting forth the rates it is placing into effect and designating that those rates as being subject to refund. 4. Kentucky Power shall, by counsel, enter an appearance in this proceeding within seven days of the date of service of this Order. The entry of appearance shall include the name, address, telephone number, fax number, and electronic mail address of counsel. 5. Unless otherwise ordered by the Commission, the procedures set forth in 807 KAR 5:001, Section 8, related to service and electronic filing of papers shall be followed in this proceeding. 6. Pursuant to 807 KAR 5:001, Section 8(9), within seven days of the date of service of this Order, Kentucky Power shall file by electronic means a written statement that it waives any right to service of Commission Orders by United States mail and that it or its authorized agent possess the facilities to receive electronic submissions. |
|
2/12/2024 10:20:35 AM
Motion to Intervene J. Michael West Office of the Attorney General |
|
1/31/2024 4:47:20 PM
Application Lerah M. Kahn Kentucky Power Company |
|
1/25/2024 4:05:15 PM
20240125_PSC Acknowledgment Letter.pdf |
|
1/25/2024
Kentucky Power Company Notice of Intent to File an Application for: (1) Approval of the Rockport Offset True-Up Amount; (2) Approval to Collect the Rockport Offset True-Up Through Tariff Purchase Power Adjustment; And (3) All Other Required Approvals and R |