Kentucky Public Service Commission


View Case Filings for: 2023-00430


Case Number:2023-00430
Service Type:Water
Filing Date:3/18/2024
Category:Regular
Utilities:

Knox County Utility Commission


Electronic Case
Case Nature:

ELECTRONIC APPLICATION OF KNOX COUNTY UTILITY COMMISSION FOR A RATE ADJUSTMENT PURSUANT TO 807 KAR 5:076









Case Filings
FilingDocuments
4/3/2024 2:38:56 PM

Order Entered: 1. The procedural schedule set forth in Appendix A to this Order shall be followed. 2. On or before the date set forth in the procedural schedule, Knox County Commission shall file its responses to the Commission Staff’s request for information, attached to this Order as Appendix B. 3. Knox County Commission shall respond to any additional requests for information propounded by Commission Staff as provided in those requests. 4. No later than the date set forth in the procedural schedule, Commission Staff shall file with the Commission and serve upon all parties of record a written report (Commission Staff’s Report) containing its recommendations regarding Knox County Commission’s requested rate adjustment. 5. No later than 14 days after the date of service of the Commission Staff’s Report, each party of record shall file with the Commission: a. Its written comments on and any objections to the findings contained in the Commission Staff’s Report; and b. Any additional evidence for the Commission to consider. 6. If Commission Staff recommends Knox County Commission’s financial condition supports a higher rate than Knox County Commission proposes or assessment of an additional rate or charge not proposed in Knox County Commission’s application, Knox County Commission in its response to Commission Staff’s Report shall state its position on whether the Commission should authorize the assessment of the higher rate or the additional rate or charge.


3/18/2024 10:02:43 AM

20240318_PSC Deficiency Cured Letter.pdf


3/18/2024 9:12:49 AM

Response to Commissions March 13, 2024, Notice of Deficiency


Kenneth Dale Taylor Knox County Utility Commission

Bridwell_Read_first_03-18-24.pdf

Transmittal Letter - Response to NOD

Notice_of_Deficiency__2_Response.pdf

Response to March 13, 2024, NOD

3/13/2024 10:26:23 AM

20240313_PSC Deficiency Letter.pdf


3/12/2024 11:51:17 PM

Response to Commission February 28, 2024 Notice of Deficiencies


Kenneth Dale Taylor Knox County Utility Commission

Bridwell_Read_first_03-12-24.pdf

Transmittal letter - NOD Response

2/28/2024 3:09:55 PM

20240228_PSC Deficiency Letter.pdf


2/27/2024 11:30:27 AM

Alternative Rate Filing Application pursuant to 807 KAR 5:076


Kenneth Dale Taylor Knox County Utility Commission

Application_Transmittal_Letter.pdf

Read first application transmittal letter.

ARFA_Package_2-26-24_Completed.pdf

Knox County Utility Commission ARF Application

12/28/2023 12:54:51 PM

20231228_PSC Acknowledgment Letter.pdf


12/28/2023

Knox County Utility Commission Notice of Intent to File an Application for a Rate Adjustment pursuant to 807 KAR 5:076 Using Electronic Filing Procedures


20231228_Knox County Utility Commission Notice of Intent and Election.pdf

Knox County Utility Commission Notice of Intent and Election