ELECTRONIC APPLICATION OF BATH COUNTY WATER DISTRICT FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT AND FINANCE IMPROVEMENT PROJECTS PURSUANT TO 278.020 AND 278.300
Case Filings | |
---|---|
Filing | Documents |
6/29/2023 3:37:31 PM
Final Order Entered: 1. Bath District is granted a CPCN to rehabilitate the six water storage tanks, to rehabilitate the Midland Pump Station, and to replace the Ore Mines Pump Station as set forth in its application. 2. Bath District shall immediately notify the Commission upon knowledge of any material changes to the projects, including but not limited to increase in cost and any significant delays. 3. Any material deviation from the construction approved by this Order shall be undertaken only with prior approval of the Commission. 4. Bath District shall file with the Commission documentation of the total costs of the projects, including the cost of construction and all other capitalized costs (e.g., engineering, legal, administrative, etc.) within 60 days of the date that construction authorized under this CPCN is substantially completed. Construction costs shall be classified into appropriate plant accounts in accordance with the Uniform System of Accounts for water utilities prescribed by the Commission. 5. Bath District shall file a copy of the as-built drawings and a certified statement that the construction has been satisfactorily completed in accordance with the contract plans and specifications within 60 days of the substantial completion of the construction certificated herein. 6. Bath District is authorized to issue the evidences of debt requested subject to the conditions discussed herein. |
|
5/31/2023 11:46:02 AM
Bath County Water District response to Commissions Staff Second Request for Information Earl Rogers III Bath County Water District |
|
5/22/2023 4:06:25 PM
Data Request |
|
5/12/2023 11:45:20 AM
Response of Bath County Water District to Commission Staff First Request for Information and read first letter Earl Rogers III Bath County Water District |
|
4/28/2023 1:13:05 PM
Data Request |
|
4/25/2023 4:50:50 PM
Order Entered: 1. Bath District’s application for approval of the proposed evidence of indebtedness is continued beyond the 60-day period specified in KRS 278.300(2). 2. The procedural schedule set forth in the Appendix to this Order shall be followed. 3. Bath District shall respond to all requests for information propounded by Commission Staff, whether identified on the procedural schedule or otherwise, as provided in those requests. 4. Any party filing a paper with the Commission shall file an electronic copy in accordance with the electronic filing procedures set forth in 807 KAR 5:001E, Section 8. Electronic documents shall be in portable document format (PDF), shall be searchable, and shall be appropriately bookmarked. The Commission directs the parties to the Commission’s July 22, 2021 Order in Case No. 2020-00085² regarding filings with the Commission. 5. As set forth in 807 KAR 5:001E, Section 4(11)(a), a person requesting permissive intervention in a Commission proceeding is required to demonstrate either (1) a special interest in the proceeding that is not adequately represented in the case, or (2) that the person requesting permissive intervention is likely to present issues or develop facts that will assist the Commission in fully considering the matter without unduly complicating or disrupting the proceedings. |
|
4/12/2023 1:57:05 PM
20230412_PSC Deficiency Cured Letter.pdf |
|
4/5/2023 1:17:19 PM
Read First Letter Response to deficiency notice and attachments Earl Rogers III Bath County Water District |
|
3/31/2023 12:28:34 PM
20230331_PSC Deficiency Letter.pdf |
|
3/28/2023 9:50:52 AM
Application for Certificate of Public Need and Necessity and to construct water system improvement projects with exhibits and read first letter. Earl Rogers III Bath County Water District |
|
3/23/2023 2:27:57 PM
Entry of Appearance of Counsel and Read First Letter Earl Rogers III Bath County Water District |
|
3/17/2023 10:32:05 AM
20230317_PSC Acknowledgment Letter.pdf |
|
3/17/2023
Bath County Water District Notice of Intent to File an Application for a Certificate of Public Convenience and Necessity to Construct and Finance a System Improvement Project Using Electronic Filing Procedures |