View Case Filings for: 2024-00337
Service Type:Electric
Filing Date:5/19/2025
Category:Merchant Plant Applications
Utilities:
Wood Duck Solar LLC
Electronic Case
ELECTRONIC APPLICATION OF WOOD DUCK SOLAR LLC FOR A CERTIFICATE OF CONSTRUCTION FOR AN APPROXIMATELY 100 MEGAWATT MERCHANT ELECTRIC SOLAR GENERATING FACILITY AND NONREGULATED TRANSMISSION LINE IN BARREN COUNTY, KENTUCKY PURSUANT TO 278.700 AND 807 KAR 5:110
Scheduled | |
---|---|
10/02/2025 | Formal Hearing |
07/01/2025 | Public Meeting |
Case Filings | |
---|---|
Filing | Documents |
6/26/2025 4:43:23 PM
Response in Opposition to Motion to Intervene Pierce Stevenson Wood Duck Solar LLC |
|
6/25/2025 1:28:53 PM
Notice of Filing Pierce T. Stevenson Wood Duck Solar LLC |
|
6/25/2025 1:28:18 PM
Notice of Filing Pierce T. Stevenson Wood Duck Solar LLC |
|
6/19/2025 3:28:35 PM
Motion to Intervene Harold Mac Johns Nancy West |
|
6/16/2025 3:21:13 PM
Order Entered: 1. A local public hearing in this matter is scheduled for July 1, 2025, at 5 p.m. Central Daylight Time, at 200 West Main Street, Glasgow, Kentucky 42141. 2. A copy of this Order shall be served upon the Barren County Judge Executive and the Chair of the Joint City-County Planning Commission. 3. Wood Duck Solar shall give timely notice of this local public hearing in a newspaper of general circulation in Barren County as required by 807 KAR 5:110, Section 9(2). 4. Wood Duck Solar shall submit proof to the Siting Board of the notice to the public at least three days prior to the July 1, 2025 hearing. |
|
6/9/2025 4:36:46 PM
Barren County Residents Request for Public Hearing |
|
6/3/2025 2:18:17 PM
Order Entered: 1. The statutory deadline for the processing of this matter is 180 days from the application filing date. 2. The procedural schedule set forth in the Appendix to this Order shall be followed for this proceeding. 3. Wood Duck Solar shall respond to all requests for information propounded by Siting Board Staff, whether identified on the procedural schedule or otherwise, as provided in those requests. 4. Pursuant to 807 KAR 5:110, Section 3(4), any party filing a paper with the Siting Board shall file an electronic copy in accordance with the electronic filing procedures set forth in 807 KAR 5:001, Section 8. Electronic documents shall be in portable document format (PDF), shall be searchable, and shall be appropriately bookmarked. The Siting Board directs the parties to the Commission’s July 22, 2021 Order in Case No. 2020-00085¹ regarding filings with the Siting Board. 5. As set forth in 807 KAR 5:110, Section 4, a person requesting to become a party to the proceeding before the Siting Board is required to demonstrate (1) that he or she has a special interest in the proceeding; or (2) that his or her participation in the proceeding will assist the Siting Board in reaching its decision and would not unduly interrupt the proceeding. 6. An evidentiary hearing in this matter shall be held on October 2, 2025, at 1PM EDT at the offices of the Public Service Commission at 211 Sower Boulevard, Frankfort, Kentucky. |
|
6/2/2025 4:29:44 PM
20250602_PSC No Deficiency Letter - Merchant Plant Application.pdf |
|
5/19/2025 4:43:33 PM
Application and Exhibits for Certificate of Construction Pierce T. Stevenson Wood Duck Solar LLC |
|
5/16/2025 1:47:39 PM
20250516_Acknowledgement Letter of Application Fees.pdf |
|
12/16/2024 4:24:07 PM
20241216_Letter Filing Letter to Governor Beshear Requesting Ad Hoc Appointment into the Record.pdf |
|
11/25/2024 4:03:42 PM
20241125_PSC No Deficiency Letter- Notice of Intent.pdf |
|
11/20/2024 1:34:23 PM
Notice of Intent Gregory T. Dutton Wood Duck Solar LLC |
|
10/18/2024 8:59:40 AM
20241018_PSC Acknowledgment Letter.pdf |
|
10/17/2024
Wood Duck Solar LLC Notice of Intent to File an Application for a Certificate of Construction for a Merchant Electric Generating Facility and Nonregulated Transmission Line Using Electronic Filing Procedures |