Service Type:Water
Filing Date:7/15/2022
Category:Regular
Utilities:
Sandy Hook Water District
Electronic Case
Case Nature:
ELECTRONIC APPLICATION OF SANDY HOOK WATER DISTRICT FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A SYSTEM IMPROVEMENTS PROJECT AND AN ORDER APPROVING AN INCREASE IN RATES AND AUTHORIZING THE ISSUANCE OF SECURITIES PURSUANT TO KRS 278.023
Case Filings | |
---|---|
Filing | Documents |
2/22/2023 3:07:41 PM
Order Entered: 1. Sandy Hook District shall file an application for a general rate adjustment pursuant to 807 KAR 5:001E, Section 16, or an application for an alternative rate adjustment pursuant to 807 KAR 5:076, or a formal motion with a detailed analysis of its rates and revenues and a statement explaining the reasons why no rate modifications are necessary by June 30, 2024. 2. The rate adjustment or detailed motion filed by Sandy Hook District on or before June 30, 2024, shall be based upon 2023 financial data and Sandy Hook District’s 2023 annual report 3. This case is closed and removed from the Commission’s docket. |
|
11/7/2022 11:46:49 AM
Notice of Start W. Randall Jones Sandy Hook Water District |
|
8/26/2022 9:58:50 AM
Affidavits of Publication W. Randall Jones Sandy Hook Water District |
|
8/23/2022 1:58:57 PM
Response to Information Request W. Randall Jones Sandy Hook Water District |
|
8/10/2022 3:53:53 PM
Order Entered: 1. Sandy Hook District is granted a CPCN for the proposed project as submitted.2. Sandy Hook District’s proposed plan of financing is approved. 3. Sandy Hook District is authorized to issue $1,180,000 of Series A Bonds maturing over a 40-year period at an interest rate not to exceed 1.125 percent annually; and $1,721,000 of Series B Bonds maturing over a 40-year period at an interest rate not to exceed 1.50 percent annually. 4. The proceeds from the issuance of the Water System Revenue Bonds shall be used only for the purposes specified in Sandy Hook District’s application. 5. Sandy Hook District shall obtain approval from the Commission prior to performing any additional construction not expressly authorized by this Order. 6. Sandy Hook District shall file with the Commission documentation of the total costs of this project, including the cost of construction and all other capitalized costs (e.g., engineering, legal, and administrative), within 60 days of the date that construction is substantially completed. Construction costs shall be classified into appropriate plant accounts in accordance with the Uniform System of Accounts for water utilities prescribed by the Commission. |
|
7/18/2022 2:17:07 PM
20220718_PSC No Deficiency Letter.pdf |
|
7/15/2022 1:37:37 PM
Application and Supporting Documents W. Randall Jones Sandy Hook Water District |
|
7/6/2022 9:56:29 AM
20220706_PSC Acknowledgment Letter.pdf |
|
7/5/2022
Sandy Hook Water District Notice of Intent to File an Application for a Certificate of Public Convenience and Necessity to Construct a System Improvements Project and an Order Approving an Increase in Rates and Authorizing the Issuance of Securities pursua |