View Case Filings for: 2020-00043


Case Number:2020-00043
Service Type:Electric
Filing Date:3/27/2020
Category:Merchant Plant Applications
Utilities:

Merchant Plant Applications - Company Not Assigned


Electronic Case
Case Nature:

Glover Creek Solar, LLC



View Public Comments regarding this case






Case Filings
FilingDocuments
1/19/2021 8:52:33 PM

Response to Staffs First Request for Information on Rehearing

M Todd Osterloh Glover Creek Solar, LLC

Glover_Creek_Reconsideration_DRs_final_public.pdf

Response to Staff's First Request for Information on Rehearing

Glover_Creek_Third_Petition_for_Confidentiality.PDF

Third Petition for Confidentiality

Read1st_Glover_Creek_Reheraing_DR1.pdf

Read1st

1/4/2021 8:53:56 AM

Data Request

20210104_DATA_REQUEST.pdf
12/18/2020 12:18:30 PM

Order Entered: 1. Glover Creek’s requests for reconsideration and clarification of the mitigation measures identified herein is granted for the purpose of conducting further investigation into those issues. 2. The procedural schedule set forth in the Appendix to this Order shall be followed.

20201218_PSC_ORDER.pdf

11/4/2020 2:55:05 PM

Motion to Strike and Modify

James W. Gardner Glover Creek Solar, LLC

Glover_Creek_Motion_to_Strike_and_Modify_(01364298xA9D25).pdf
Read1st_Glover_Creek_Motion_to_Strike_(01364303xA9D25).pdf

Read1st

10/19/2020 4:54:15 PM

Petition for Reconsideration

James W. Gardner Glover Creek Solar, LLC

Glover_Creek_Petition_for_Reconsideration_final_(01355558xA9D25).pdf
Read1st_Glover_Creek_Petition_(01355681xA9D25).pdf

Read1st

10/2/2020 7:29:07 AM

Order Entered: 1. Glover Creek's petition for confidential protection for the information contained in its discovery responses to Siting Board Staff's and Harvey Economics' Second Requests for Information, Item 1, is granted. 2. The designated information contained in Glover Creek's discovery responses to Siting Board Staff's and Harvey Economics' Second Requests for Information, Item1, shall not be placed in the public record or made available for public inspection for an indefinite period or until further Order of this Siting Board. 3. Use of the material in question in any Siting Board proceeding shall be in compliance with 807 KAR 5:001, Section 13(9). 4. Glover Creek shall inform the Siting Board if the material in question becomes publicly available or no longer qualifies for confidential treatment.

20201002_PSC_ORDER.pdf

9/23/2020 3:04:38 PM

Final Order Entered: 1. Glover Creek's Application for a Certificate to Construct an approximately 55 MWac merchant solar electric generating facility in Metcalfe County, Kentucky is conditionally granted subject to full compliance with the mitigation measures and condition prescribed in Appendix A. 2. Glover Creek's motion for deviation from the 2,000 feet setback requirement is granted except for the location of the inverters. 3. Glover Creek shall fully comply with the mitigation measures and conditions prescribed in Appendix A.

20200923_PSC_ORDER01.pdf

9/23/2020 9:32:52 AM

Order Entered: 1. Glover Creek's petition for confidential protection for the information contained in its discovery responses to Siting Board Staff's First Requests for Information, Items 3, 7, and Exhibit K is granted. 2. The designated information contained in in Glover Creek's discovery responses to Siting Board Staff's First Requests for Information, Items 3, 7, and Exhibit K shall not be placed in the public record or made available for public inspection for an indefinite period or until further Order of this Siting Board. 3. Use of the material in question in any Siting Board proceeding shall be in compliance with 807 KAR 5:001, Section 13(9). 4. Glover Creek shall inform the Siting Board if the material in question becomes publicly available or no longer qualifies for confidential treatment. 5. If a nonparty to this proceeding requests to inspect the material granted confidential treatment by this Order and the period during which the material has been granted confidential treatment has not expired, Glover Creek shall have 30 days from receipt of written notice of the request to demonstrate that the material still falls within the exclusions from disclosure requirements established in KRS 61.878. If Glover Creek is unable to make such demonstration, the requested material shall be made available for inspection. Otherwise, the Siting Board shall deny the request for inspection.

20200923_PSC_ORDER.pdf

7/24/2020 4:31:53 PM

Response to Harvey Economics Report

James W. Gardner Glover Creek Solar, LLC

Read1st_Glover_Creek_Response_to_Consultant_Report_(01312491xA9D25).pdf

Read1st

Response_to_Harvey_Economics_Final_(01312776xA9D25).pdf

Glover Creek's Response to Harvey Economics Report

7/10/2020 1:22:39 PM

20200710_Letter Filing Report into the Record.pdf

20200710_Letter Filing Report into the Record.pdf
6/29/2020 7:50:46 PM

Responses to Second Requests for Information from the Siting Board and Harvey Economics, as well as a Petition for Confidentiality

M. Todd Osterloh Glover Creek Solar, LLC

01301350.PDF

Glover Creek Response to Harvey Economics 2nd RFI

Glover_Creek_Response_to_Siting_Board_2nd_RFI_6-29-20_(01301348xA9D25).pdf

Glover Creek Response to Siting Board 2nd RFI

Glover_Creek_Second_Petition_for_Confidentiality_6-29-20_(01301355xA9D25).pdf

Glover Creek 2nd Petition for Confidentiality

Read1st_Glover_Creek_2nd_RFI_(01301353xA9D25).pdf

Read 1st Letter Glover Creek 2nd RFI

6/24/2020 1:52:03 PM

Corrected Exhibit M to Glover Creeks Exhibit M of its Responses to Initial Requests for Information.

James W. Gardner Glover Creek Solar

Corrected_Exhibit_M_Glover_Creek_Glare_Studies_(01299076xA9D25).pdf

Corrected Exhibit M to Glover Creek's Exhibit M of its Responses to Initial Requests for Information

Read1st_Glover_Creek_Corrected_Exhibit_M_(01299073xA9D25).pdf

Read1st

6/15/2020 6:02:51 PM

Supplemental Response to Harvey Economics First Data Request, Item XII(F)

James W. Gardner Glover Creek Solar, LLC

Glover_Creek_Supplemental_Response_to_HE_12F_(01294220xA9D25).pdf

Supplemental Response to Harvey Economics' First Data Request, Item XII(F)

Read1st_Glover_Creek_Supplement_HE_XII(F)_(01294223xA9D25).pdf

Read1st

6/12/2020 3:39:40 PM

Data Request

20200612_DATA_REQUEST.pdf
6/1/2020 10:13:50 PM

Response to First Request for Information

M Todd Osterloh Glover Creek Solar, LLC

Exhibit_A2_Glover_Creek_Layout_for_Dec2019_meetings_-_reduced.pdf_(01285416xA9D25).pdf

Exhibit 1B

Glover_Creek_Exhibit_A1_(01285952xA9D25).pdf

Exhibit 1A

Glover_Creek_Petition_for_Confidentiality_(01285946xA9D25).pdf

Petition for Confidentiality

Glover_Creek_Response_to_Siting_Board_First_-_PUBLIC_(01285936xA9D25).pdf

Response to Siting Board's First Request for Information

Glover_Creek_Responses_to_Harvey_Economics_First_Request_Final_(01285940xA9D25).pdf

Response to Harvey Economics' First Request for Information

Read1st_Glover_Creek_First_RFI_(01285955xA9D25).pdf

Read1st

5/29/2020 3:37:30 PM

20200529_Chairman Schmitt Letter to Metcalfe County Judge Harold Stilts Designating as Vice Chairman.pdf

20200529_Chairman Schmitt Letter to Metcalfe County Judge Harold Stilts Designating as Vice Chairman.pdf
5/14/2020 9:23:21 AM

Data Request

20200514_DATA_REQUEST.pdf
5/13/2020 10:12:36 AM

20200513_Memo Filing Procedural Schedule and Extending Deadline.pdf

20200513_Memo Filing Procedural Schedule and Extending Deadline.pdf
4/29/2020 7:51:34 AM

20200429_Memo Filing Document.pdf

20200429_Memo Filing Document.pdf
4/20/2020 3:09:38 PM

Motion to Deviate from Setback Requirements

Todd Osterloh Glover Creek Solar

Glover_Creek_Motion_for_Deviation_from_Setback_Requirements_(01269780xA9D25).pdf
Read1st_Glover_Creek_Motion_for_Deviation_(01269806xA9D25).pdf

Read1st

3/31/2020 4:27:30 PM

20200331_Acknowledgement Letter of Application Fees.pdf

20200331_Acknowledgement Letter of Application Fees.pdf
3/31/2020 2:30:56 PM

20200331_No Deficiency Letter.pdf

20200331_No Deficiency Letter.pdf
3/27/2020 1:34:38 PM

Application for a Construction Certificate

M Todd Osterloh Glover Creek Solar

Glover_Creek_Pleading_Application_Final_(01260341xA9D25).pdf

Application

Glover_Creek_Solar_Site_Assessment_Report_Volume_2_Final_(01260304xA9D25).pdf

Application Volume 2

Glover_Creek_Solar_Siting_Board_Application_Volume_1_Final_(01260356xA9D25).pdf

Application Volume 1

Read1st_Glover_Creek_Application_(01260525xA9D25).pdf

Read1st

2/27/2020 10:51:42 AM

20200227_Letter Filing Chairman Schmitt Letter to Metcalfe County Judge Executive into the Record.pdf

20200227_Letter Filing Chairman Schmitt Letter to Metcalfe County Judge Executive into the Record.pdf
2/27/2020 10:50:04 AM

20200227_Letter Filing Chairman Schmitt Letter to Governor Beshear into the Record.pdf

20200227_Letter Filing Chairman Schmitt Letter to Governor Beshear into the Record.pdf
2/12/2020

20200212_PSC Acknowledgment Letter.pdf

20200212_PSC Acknowledgment Letter.pdf
2/10/2020

Glover Solar, LLC Notice of Intent to File an Application for a Certificate of Public Convenience and Necessity to Construct an Approximately 55 Megawatt Merchant Electric Solar Generating Facility in Metcalfe County, Kentucky pursuant to KRS 278.700 and 8

20200210_Glover Solar, LLC Notice of Intent.pdf

Glover Solar, LLC Notice of Intent