Governor issues Emergency Order - KYTC order linked below applies to commercial vehicles responding to affected areas for utility restoration activities.
Also an Emergency Relief letter has been issued by KY PSC the Commission notes that the conditions created from the severe weather meet the definition of emergency under KRS 367.4903(7) please see the KYTC 1-22-2026 Order: and PSC Emergency Locate Relief 1-22-2026 Order:

Kentucky Public Service Commission


View Post Case Referenced Correspondence for: 2021-00333


Case Number:2021-00333
Service Type:Water
Filing Date:9/1/2021
Category:Regular
Utilities:

North Marshall Water District


Electronic Case

ELECTRONIC APPLICATION OF NORTH MARSHALL WATER DISTRICT FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A SYSTEM IMPROVEMENTS PROJECT AND AN ORDER APPROVING A CHANGE IN RATES AND AUTHORIZING THE ISSUANCE OF SECURITIES PURSUANT TO KRS 278.023









Post Case Referenced Correspondence
FilingDocuments
11/15/2023 3:29:20 PM

Tabulation of final project cost summarized by uniform accounts for plant


Roger Colburn

CASE_NO_2021-00333_ITEM_6_REV1.0.xlsx

Capital Project Expense Breakdown by Vendor Classified by Uniform Account Code

Read1st.pdf

General Summary and Description of Filing

11/15/2023 3:23:11 PM

This filing is the Engineers Certificate of Construction Completion and submittal of As-Built Drawings addressing Item 7 of the Commissions Sept. 17, 2021 order for Case 2021-00333


Roger Colburn

Case_No._2021-00333_AsBuilt_DWGS.pdf

Record As-Built Engineering Drawings

Engineers_Certication_of_Project_Construction_-_Signed.pdf

Engineer's Certification of Project Completion

Read1st.pdf

Summary description of documents being filed

2/23/2023 2:28:41 PM

Status report regarding cost of service review and rate analysis


Roger Colburn

2/10/2023 5:14:23 PM

Notification of construction completion and request for extension of deadline for filing final documents


Roger Colburn

NMWD_2021_00333_CONSTRUCTION_COMPLETION_NOTIFICATION_EXTENSION_REQUEST.pdf

Letter to Executive Director with notification of construction project completion date and request for an extension of deadline for filing final documents related to case.

6/17/2022 10:48:57 AM

Post Case Filings


W. Randall Jones

NMWD_2021_00333_50_percent_CONST_NOTIFICATION.pdf

50 percent construction completion letter