View Case Filings for: 2025-00007
Service Type:Water
Filing Date:2/2/2025
Category:Regular
Utilities:
Northern Kentucky Water District
Electronic Case
Case Nature:
ELECTRONIC APPLICATION OF NORTHERN KENTUCKY WATER DISTRICT FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY AND APPROVAL OF FINANCING FOR THE CONSTRUCTION OF NEWPORT WATER MAIN REPLACEMENT PHASE 1 AND PHASE 2
Case Filings | |
---|---|
Filing | Documents |
4/3/2025 12:58:35 PM
Final Order Entered: 1. Northern Kentucky District is granted a CPCN to replace water lines and water mains, as proposed in its application. 2. Northern Kentucky District shall immediately notify the Commission upon knowledge of any material changes to the projects, including but not limited to increase in cost and any significant delays. 3. Any material deviation from the construction approved by this Order shall be undertaken only with prior approval of the Commission. 4. Northen Kentucky District shall file with the Commission documentation of total costs of the projects, including the cost of construction and all other capitalized costs (e.g., engineering, legal, administrative, etc.) within 60 days of the date that the construction authorization under this CPCN is substantially completed. Construction costs shall be classified into appropriate plant accounts in accordance with the Uniform System of Accounts for water utilities prescribed by the Commission. 5. Northern Kentucky District shall file a certified statement that the construction has been satisfactorily completed in accordance with the construction plans and specifications within in 60 days of the substantial completion of the construction discussed herein. 6. Northern Kentucky District is authorized to issue the evidence of debt requested subject to the conditions set forth in its application and discussed herein. |
|
3/18/2025 11:01:08 PM
Motion for Decision on the Record and Waiver of Hearing Tom Edge Northern Kentucky Water District |
|
2/25/2025 7:37:00 PM
Response to Commission Staffs Request for Information Tom Edge Northern Kentucky Water District |
|
2/17/2025 4:53:49 PM
Data Request |
|
2/7/2025 10:30:13 AM
Order Entered: 1. The procedural schedule set forth in the Appendix to this Order shall be followed. 2. Northern Kentucky District shall respond to all requests for information propounded by Commission Staff, whether identified on the procedural schedule or otherwise, as provided in those requests. 3. Any party filing a paper with the Commission shall file an electronic copy in accordance with the electronic filing procedures set forth in 807 KAR 5:001, Section 8. Electronic documents shall be in portable document format (PDF), shall be searchable, and shall be appropriately bookmarked. The Commission directs the parties to the Commission’s July 22, 2021 Order in Case No. 2020-00085 regarding filings with the Commission. 4. As set forth in 807 KAR 5:001, Section 4(11)(a), a person requesting permissive intervention in a Commission proceeding is required to demonstrate either (1) a special interest in the proceeding that is not adequately represented in the case, or (2) that the person requesting permissive intervention is likely to present issues or develop facts that will assist the Commission in fully considering the matter without unduly complicating or disrupting the proceedings. |
|
2/3/2025 3:58:19 PM
20250203_PSC Deficiency Cured Letter.pdf |
|
2/2/2025 12:09:53 PM
Response to Notice of Filing Deficiency Tom Edge Northern Kentucky Water District |
|
1/24/2025 1:42:38 PM
20250124_PSC Deficiency Letter.pdf |
|
1/21/2025 3:02:08 PM
Application and Exhibits Tom Edge Northern Kentucky Water District |
|
1/13/2025 3:23:48 PM
20250113_PSC Acknowledgment Letter.pdf |
|
1/13/2025
Northern Kentucky Water District Notice of Intent to File an Application for a Certificate of Public Convenience and Necessity and Approval of Financing for the Construction of Newport Water Main Replacement Phase 1 and Phase 2 Using Electronic Filing Proc |