Kentucky Public Service Commission


View Case Filings for: 2023-00013


Case Number:2023-00013
Service Type:Electric
Filing Date:9/6/2023
Category:Fuel Adjustment Clause
Utilities:

Big Rivers Electric Corporation


Electronic Case
Case Nature:

AN ELECTRONIC EXAMINATION OF THE APPLICATION OF THE FUEL ADJUSTMENT CLAUSE OF BIG RIVERS ELECTRIC CORPORATION FROM NOVEMBER 1, 2020 THROUGH OCTOBER 31, 2022









Case Filings
FilingDocuments
5/6/2024 5:53:33 PM

Final Order Entered: 1. The charges and credits applied by BREC through the FAC for the period from November 1, 2020, through October 31, 2022, are approved. 2. BREC's continued use of the existing base fuel cost of $0.020932 per kWh is approved. 3. This case is closed and removed from the Commission’s docket.


5/6/2024 5:51:31 PM

Order Entered: 1. The charges and credits billed by BREC through its FAC from May 1, 2021, through October 31, 2021, are approved. 2. The charges and credits billed by BREC through its FAC from November 1, 2021, through April 30, 2022, are approved. 3. A copy of this Order shall be entered into the record in Case Nos. 2022-00041 and 2022-00268.


2/29/2024 12:49:36 PM

20240229_PSC Notice of Filing Hearing Documents - January 4, 2024.pdf


1/29/2024 4:47:01 PM

Order Entered: 1. BREC’s September 22, 2023 motion for confidential treatment is granted in part and denied in part regarding time period. 2. BREC’s responses to Staff’s First Request, Items 12 and 13, granted confidential treatment by this Order shall not be placed in the public record or made available for public inspection for ten years or until further order of this Commission. 3. BREC’s responses to Staff’s First Request, Items 32, 33, 34, and redactions from the Wright Direct Testimony, granted confidential treatment by this Order shall not be placed in the public record or made available for public inspection for five years or until further order of this Commission. 4. BREC’s October 20, 2023 motion for confidential treatment is granted in part and denied in part regarding time period. 5. BREC’s responses to Staff’s Second Request, Items 1, 3, 4, 5, 6, and 26, granted confidential treatment by this Order shall not be placed in the public record or made available for public inspection for five years or until further order of this Commission.


1/25/2024 1:08:03 PM

Big Rivers Response to Commission Staffs Post-Hearing Information Request and Supplemental Response to Item 4 of Commission Staffs Third Request for Information


Senthia Santana Big Rivers Electric Corporation

BR_Rsp_to_Post-Hearing_IR.pdf

Big Rivers' Response to the Commission Staff's Post-Hearing Information Request

BR_Supp_Rsp_to_PSC_3-4.pdf

Big Rivers' Supplemental Response to Item 4 of the Commission Staff's Third Request for Information

CN_2023-00013_-_2-Yr_FAC_CNF_Motion.pdf

Big Rivers' Motion for Confidential Treatment

1/16/2024 1:30:05 PM

IT IS THEREFORE ORDERED that BREC’s motion to deviate from the requirements of 807 KAR 5:001, Section 9(2)(b) is granted.


1/11/2024 2:35:17 PM

Data Request


1/9/2024 2:42:56 PM

Order Entered: 1. Post-hearing requests for information shall be filed on or before January 11, 2024. 2. Responses to post-hearing requests for information shall be filed on or before January 25, 2024.


1/5/2024 12:59:30 PM

Motion for Approval to Deviate from Rule


Senthia Santana Big Rivers Electric Corporation

CN_2023-00013_-_Approval_to_Deviate_from_Rule.pdf

Big Rivers' Motion to Deviate from Rule

1/3/2024 5:32:57 PM

Big Rivers Proof of Publication - Hearing Notice


Senthia Santana Big Rivers Electric Corporation

0.0_Tearsheets_1_of_2.pdf

Tearsheets 1 of 2

0.0_Tearsheets_2_of_2.pdf

Tearsheets 2 of 2

Affidavit.pdf

Affidavit of Publication

1/3/2024 3:48:32 PM

Order Entered: 1. BREC’s motion for Ms. Payne to appear virtually in the hearing on January 4, 2024, is granted. 2. Commission Staff shall contact participants with instructions for participating remotely.


1/2/2024 3:56:02 PM

Big Rivers Motion for Leave for a Witness to Participate Virtually in the January 4, 2024 Hearing


Senthia T Santana Big Rivers Electric Corporation

CN_2023-00013_-_2-Yr_FAC_Virtual_Appearance_Hearing.pdf

Big Rivers' Motion for Leave for A Witness to Appear Virtually

12/13/2023 6:40:22 PM

Big Rivers Notice of Substituting Witness


Senthia T Santana Big Rivers Electric Corporation

Read_1st_Letter-_Notice_Substitution_of_Witness.pdf

Read 1st - Notice of Substitution of Witness

12/12/2023 12:32:51 PM

Duplicate of Notice of Hearing and Request for Publication


Senthia Santana Big Rivers Electric Corporation

11/20/2023 1:46:03 PM

Order Entered: 1. A hearing in this matter shall be held on January 4, 2024, at 9 a.m. Eastern Standard Time and continuing until called from the bench by the presiding officer, in the Richard Raff Hearing Room at the offices of the Public Service Commission at 211 Sower Boulevard, Frankfort, Kentucky. 2. Pursuant to 807 KAR 5:001, Section 2, if the hearing is not concluded on the designated day, the hearing may be continued upon verbal announcement by the presiding officer. A verbal announcement made by the presiding officer shall be proper notice of the continued hearing. 3. Witnesses who sponsor schedules, testimony, or responses to requests for information shall participate in person at the January 4, 2024 hearing. 4. Big Rivers Electric Corporation (BREC) shall give notice of the hearing in compliance with 807 KAR 5:001, Section 9(2)(b).


11/16/2023 10:43:21 AM

Big Rivers Response to the Commission Staffs Third Request for Information and Motion for Confidential Treatment


Senthia Santana Big Rivers Electric Corporation

CN_2023-00013_-_CNF_Motion.pdf

Big Rivers' Motion for Confidential Treatment

CN_2023-00013_BR_Rsp_to_PSC_3rd_IR.pdf

Big Rivers' Response to the Commission Staff's Third Request for Information

11/1/2023 4:02:25 PM

Data Request


10/20/2023 12:57:27 PM

Response to Commission Staffs Second Request for Information and Motion for Confidential Treatment


Senthia Santana Big Rivers Electric Corporation

CN_2023-00013-Full_Rsp_to_2nd_IRs_-_Redacted.pdf

Big Rivers' Response to the Commission Staff's Second Request for Information

CN_2023-00013_-_CNF_Motion.pdf

Motion for Confidential Treatment

10/5/2023 1:02:09 PM

Data Request


9/22/2023 11:12:51 AM

Big Rivers Responses and Direct Testimony, Pursuant to the Commissions Sept. 6, 2023 Order, and Motion for Confidential Treatment


Senthia Santana Big Rivers Electric Corporation

CN_2023-00013_-_1st_Staff_FAC_DRs_-_Redacted.pdf

Big Rivers' Response to Commission's Requests for Information in Appendix B of the Sept. 6, 2023 Order

CN_2023-00013_-_Motion_for_CNF_Treatment.pdf

Big Rivers' Motion for Confidential Treatment

CN_2023-00013_-_Payne_Testimony.pdf

Direct Testimony of Vicky L. Payne

CN_2023-00013_-_PSC_1-17_Attachment.xlsx

Attachment to Big Rivers' Response to Item No. 17

CN_2023-00013_-_Wright_Testimony_Redacted.pdf

Direct Testimony of Terry Wright, Jr.

Read_1st_Letter.pdf

Read 1st Letter

9/14/2023 11:32:50 AM

Big Rivers 807 KAR 5:001 Section 8(10)(b) Certificate


Senthia Santana Big Rivers Electric Corporation

Read1st_and_Sec._8(10)(b)_Certificate.pdf

807 KAR 5:001 Section 8(10)(b) Certificate

9/6/2023 9:54:35 AM

Order Entered: 1. The procedural schedule set forth in Appendix A to this Order shall be followed. 2. On or before the date set forth in the procedural schedule, BREC shall file its responses to the Commission Staff’s request for information, attached to this Order as Appendix B. 3. BREC shall respond to any additional requests for information propounded by Commission Staff as provided in those requests. 4. BREC shall file with the Commission, no later than the date set forth in the procedural schedule attached as Appendix A, written direct testimony of the witnesses BREC intends to call at the scheduled hearing in this matter.