Kentucky Public Service Commission


View Case Filings for: 2022-00041


Case Number:2022-00041
Service Type:Electric
Filing Date:3/31/2022
Category:Fuel Adjustment Clause
Utilities:

Big Rivers Electric Corporation


Electronic Case
Case Nature:

AN ELECTRONIC EXAMINATION OF THE APPLICATION OF THE FUEL ADJUSTMENT CLAUSE OF BIG RIVERS ELECTRIC CORPORATION FROM MAY 1, 2021 THROUGH OCTOBER 31, 2021









Case Filings
FilingDocuments
5/9/2024 12:27:00 PM

Order Entered: this case is closed and removed from the docket.


12/1/2023 3:35:03 PM

20231201_PSC Notice of Filing.pdf


6/26/2023 8:55:43 AM

Big Rivers Response to Requests to Inspect Confidential Fuel Bid Sheets


Senthia Santana Big Rivers Electric Corporation

CN_2022-00041_-_BR_Rsp_to_Requests_for_CNF_Info.pdf

Big Rivers' Response to Requests for Confidential Fuel Bid Sheets

6/8/2023 8:46:40 AM

Order Entered: within 20 days of the date of service of this Order, BREC shall file a response to Foresight’s request to review confidential fuel bid sheets.


2/15/2023 11:35:00 AM

Big Rivers Notice of Change of Address for Counsel


Senthia Santana Big Rivers Electric Corporation

CN_2022-00041_-_Change_of_Address.pdf

Big Rivers' Notice of Change of Address for Counsel

Read1st_Letter.pdf

Read 1st Letter

1/10/2023 1:56:26 PM

Order Entered: 1. BREC’s April 14, 2022, May 19, 2022, and July 28, 2022 motions for confidential treatment are granted. 2. Redactions from BREC’s response to Staff’s First Request, Item 4, pertaining to scheduled outages shall not be placed in the public record or made available for public inspection for two years or until further Order of this Commission. 3. Redactions from BREC’s response to Staff’s First Request, Items 4 and 5, pertaining to fuel solicitation, and amended responses to Items 5 and 21, shall not be placed in the public record or made available for public inspection for five years or until further Order of this Commission.


9/15/2022 3:20:26 PM

20220915_PSC Notice of Filing Hearing Documents.pdf


8/18/2022 11:13:38 AM

Big Rivers Response to the Commission Staffs Post Hearing Request for Information


Senthia Santana Big Rivers Electric Corporation

CN_2022-00041_-_Rsp_to_Post_Hearing_IRs.pdf

Big Rivers' Response to Post-Hearing Information Request

Read1st_Letter.pdf

Read 1st Letter

8/8/2022 5:40:11 PM

Data Request


8/8/2022 5:18:27 PM

Order Entered: 1. Post-hearing data requests, if any, shall be filed on or before August 8, 2022. 2. Responses to post-hearing data requests shall be filed on or before August 18, 2022. 3. This case shall stand submitted for a decision by the Commission effective 12:01 a.m. Eastern Daylight Time, September 20, 2022.


7/28/2022 5:08:34 PM

Amended Responses to Items 4 and 21 of Commission Staffs First Request for Information


Senthia Santana Big Rivers Electric Corporation

2022-07-28_Amended_Items_4_and_21_(PBL).pdf

Amended Responses to Items 4 and 21 of the Information Requests in the Appendix to the Commission's March 31, 2022 Order

Motion_for_CNF_Treatment_-_Amd_Responses.pdf

Motion for Confidential Treatment

Read1st_Letter.pdf

Read 1st Letter

7/28/2022 4:52:25 PM

Proof of Publication of Hearing Notice


Senthia Santana Big Rivers Electric Corporation

Affidavit__Tearsheets.pdf

Notarized Proof of Publication and Tearsheets

Read1st_Letter.pdf

Read 1st Letter

7/15/2022 3:11:01 PM

Request for Newspaper Publication of Hearing Notice


Senthia Santana Big Rivers Electric Corporation

Read_1st_Letter.pdf

Read 1st Letter

7/13/2022 3:25:41 PM

Order Entered: 1. A hearing in this matter shall be held on August 4, 2022, at 9 a.m. Eastern Daylight Time, in the Richard Raff Hearing Room at the offices of the Public Service Commission at 211 Sower Boulevard, Frankfort, Kentucky. 2. Big Rivers Electric Corporation (BREC) shall give notice of the hearing in compliance with 807 KAR 5:001, Section 9(2)(b). In addition, the notice of hearing shall include the following statements: “This hearing will be streamed live and may be viewed on the PSC website, psc.ky.gov”; and “Public comments may be made at the beginning of the hearing. Those wishing to make oral public comments may do so by following the instructions listed on the PSC website, psc.ky.gov.” At the time the notice is mailed or publication is requested, BREC shall forward a duplicate of the notice and request to the Commission. 3. Pursuant to KRS 278.360 and 807 KAR 5:001, Section 9(9), a digital video transcript shall be made of the hearing.


6/16/2022 5:38:26 PM

Big Rivers Response to the Commission Staffs Third Request for Information


Senthia Santana Big Rivers Electric Corporation

BRs_Resp_to_3rd_IRs.pdf

Big Rivers' Response to the Commission Staff's Third Request for Information Dated June 7, 2022

Read1st_Letter.pdf

Read 1st Letter

6/7/2022 2:28:46 PM

Data Request


6/2/2022 4:10:12 PM

Big Rivers Request for a Decision on the Record


Senthia Santana Big Rivers Electric Corporation

Read1st_Letter_-_Decision_on_Record.pdf

Request for Decision on the Record

5/19/2022 11:36:06 AM

Big Rivers Amended Responses to the Commission Staffs 1st Information Requests, Items 5 and 21


Tyson Kamuf Big Rivers Electric Corporation

Big_Rivers_Amended_Responses_-_Redacted.pdf

Big Rivers' Amended Responses to Items 5 and 21 of the Commission Staff's First Request for Information

Motion_for_CNF_Treatment.pdf

Motion for Confidential Treatment

Read1st_Letter.pdf

Read 1st Letter

5/18/2022 10:33:03 AM

Big Rivers Responses to the Commission Staffs Second Request for Information


Tyson Kamuf Big Rivers Electric Corporation

CN_2022-00041_-_2nd_Staff_FAC_DRs.pdf

Big Rivers' Responses to the Commission Staff's Second Request for Information

Read1st_Letter.pdf

Read 1st Letter

5/9/2022 8:50:12 AM

Data Request


4/14/2022 1:58:50 PM

Big Rivers Response to Commission Staffs First Request for Information


Tyson Kamuf Big Rivers Electric Corporation

BR_Rsps_to_Staffs_1st_Information_Request.pdf

Big Rivers' Response to the Commission Staff's First Request for Information

Motion_for_CNF_Treatment_-_6-Mos_FAC.pdf

Big Rivers' Motion for Confidential Treatment

Read1st_Letter.pdf

Read 1st Letter

4/1/2022 12:06:51 PM

807 KAR 5:001 Section 8(10)(b) Certificate


Tyson Kamuf Big Rivers Electric Corporation

BR_Read1st_and_Sec._8(10)(b)_Certificate.pdf

Big Rivers Electric Corporation's statement pursuant to 807 KAR 5:001 Section 8(10)(b)

3/31/2022 9:00:38 AM

Order Entered: 1. BREC, pursuant to 807 KAR 5:001, shall file its responses to the Commission’s Staff’s First Request for Information, attached to this Order as an Appendix. The information requested in the Appendix to this Order is due on April 15, 2022. The Commission directs BREC to the Commission’s July 22, 2021 Order in Case No. 2020-00085¹ regarding filings with the Commission.