View Case Filings for: 2020-00120
Service Type:Radio - Telephone
Filing Date:4/9/2020
Category:Regular
Utilities:
New Cingular Wireless PCS, LLC
Electronic Case
Case Nature:
Anneta Road Site; 7030 Anneta Road, Leitchfield, KY 42754
Case Filings | |
---|---|
Filing | Documents |
6/9/2020 9:52:56 AM
Final Order Entered: 1. AT&T Mobility is granted a CPCN to construct a wireless telecommunications facility. The proposed facility consists of a tower not to exceed 156 feet in height, with attached antennas, to be located at 7030 Anneta Road, Leitchfield, Kentucky 42754. The coordinates for the proposed facility are North Latitude 37°24'17.81" by West Longitude 86°14'17.13". 2. AT&T Mobility shall immediately notify the Commission in writing if, after the antenna tower is built and utility service is commenced, the tower is not used for three months in the manner authorized by this Order. 3. AT&T Mobility shall file a copy of the final decision regarding the pending KAZC application for the proposed construction within ten days of receiving the decision. 4. Documents filed, if any, in the future pursuant to ordering paragraphs 2 and 3 herein shall reference this case number and shall be retained in the post-case correspondence file. 5. This case is closed and removed from the Commission's docket. |
|
4/22/2020 10:46:04 AM
Order Entered: 1. AT&T Mobility's request, via electronic mail, to convert this proceeding to an electronic case is granted. 2. Electronic filing procedures shall be followed, pursuant to 807 KAR 5:001, Section 8, for all filings in this case. 3. Parties shall upload an electronic version using the Commission's Electronic Filing System. 4. Pursuant to the Commission's March 16, 2020 and March 24, 2020 Orders in Case No. 2020-00085, parties shall not file an original paper copy of any documents in this proceeding until further order of the Commission. Upon an order lifting the current state of emergency, parties shall file original paper copies of electronic documents filed in this proceeding within 30 days of the lifting of the current state of emergency. 5. The style of this case is revised to read, "Electronic Application of New Cingular Wireless PCS, LLC D/B/A AT&T Mobility for Issuance of a Certificate of Public Convenience and Necessity to Construct a Wireless Communications Facility in the Commonwealth of Kentucky in the County of Grayson." 6. Pursuant to 807 KAR 5:001, Section 8(9), within seven days of entry of this Order, AT&T Mobility shall file a written statement with the Commission that: a. Certifies that it, or its agent, possesses the facilities to receive electronic transmissions; and b. Sets forth the electronic mail address to which all electronic notices and messages related to this proceeding should be served. |
|
4/9/2020
New Cingular Wireless PCS, LLC d/b/a AT&T Mobility Application for Issuance of a Certificate of Public Convenience and Necessity to Construct a Wireless Communications Facility in the Commonwealth of Kentucky in the County of Grayson |
|
4/9/2020
No deficiency letter |
|
4/9/2020
Acknowledge Receipt of Filing |