View Case Filings for: 2018-00418
Service Type:Electric
Filing Date:12/21/2018
Category:Regular
Utilities:
Kentucky Power Company
Electronic Case
Case Nature:
ELECTRONIC APPLICATION OF KENTUCKY POWER COMPANY FOR APPROVAL OF A CONTRACT FOR ELECTRIC SERVICE WITH BRAIDY INDUSTRIES INC.
Case Filings | |
---|---|
Filing | Documents |
3/1/2023 3:57:33 PM
Final Order Entered: 1. Kentucky Power’s motion to withdraw the application is granted. 2. This case is closed and removed from the Commission’s docket. |
|
10/21/2022 1:19:35 PM
Motion to Withdraw. Lerah M Scott Kentucky Power Company |
|
2/24/2022 2:44:42 PM
Kentucky Power Companys response to Commission Staffs February 18, 2022 data request. Lerah M Scott Kentucky Power |
|
2/18/2022 9:40:52 AM
Data Request |
|
2/14/2020 10:54:24 AM
Kentucky Power filing of supplemental response to KPSC 3_1_c. Scott E. Bishop Kentucky Power Company |
|
8/20/2019 12:47:47 PM
Order Entered: 1. The motions for confidential treatment filed by Kentucky Power on December 21, 2018, and February 8, 2019, are granted. 2. The designated materials for which Kentucky Power seeks confidential treatment in its December 21, 2018 motion shall not be placed in the public record or made available for public inspection for ten years or until further Orders of this Commission. 3. The designated materials for which Kentucky Power seeks confidential treatment in its February 8, 2019 motion shall not be placed in the public record or made available for public inspection until February 8, 2021, or until further Orders of this Commission. 4. Use of the materials in question in any Commission proceeding shall be in compliance with 807 KAR 5:001, Section 13(9). 5. Kentucky Power shall inform the Commission if the materials in question become publicly available or no longer qualify for confidential treatment. 6. If a non-party to this proceeding requests to inspect the materials granted confidential treatment by this Order and the period during which the materials have been granted confidential treatment has not run, then Kentucky Power shall have 30 days from receipt of written notice of the request to demonstrate that the materials still fall within the exclusions from disclosure requirements established in KRS 61.878. If Kentucky Power is unable to make such demonstration, the requested materials shall be made available for inspection. |
|
8/12/2019 12:43:53 PM
Read 1st and Kentucky Power Companys August 12, 2019 responses to the Commissions July 30, 2019 requests. Lerah Scott Kentucky Power Company |
|
7/30/2019 2:04:05 PM
Data Request |
|
3/12/2019 1:32:15 PM
Read 1st and Kentucky Power Companys March 12, 2019 supplemental response to KPSC 1-4. Lerah Scott Kentucky Power Company |
|
3/4/2019 3:07:34 PM
Read 1st, KPCO responses to Staffs February 22, 2019 data requests and KPCO motion to submit on the record. Lerah Scott Kentucky Power Company |
|
2/22/2019 8:49:56 AM
Data Request |
|
2/8/2019 11:12:21 AM
Read 1st, KPCOs Responses to Staffs January 23, 2019 Data Requests, and KPCOs Motion for Confidential Treatment. Lerah Scott Kentucky Power Company |
|
1/23/2019 10:32:43 AM
Data Request |
|
1/4/2019 3:08:41 PM
Order Entered: 1. The procedural schedule set forth in the Appendix to this Order shall be followed in this proceeding. 2. a. Responses to requests for information shall be appropriately bound, tabbed, and indexed and shall include the name of the witness responsible for responding to the questions related to the information provided, with copies to all parties of record, the original and an electronic version to the Commission. Responses that are required to be provided on electronic medium shall be in portable document format (PDF), shall be searchable and shall be appropriately bookmarked. b. Each response shall be answered under oath, or for representatives of a public or private corporation or a partnership or an association or a governmental agency, be accompanied by a signed certification of the preparer or person supervising the preparation of the response on behalf of the entity that the response is true and accurate to the best of that person's knowledge, information, and belief formed after a reasonable inquiry. c. Any party shall make timely amendment to any prior response if it obtains information which indicates that the response was incorrect when made or, though correct when made, is now incorrect in any material respect. d. For any request to which a party fails or refuses to furnish all or part of the requested information, that party shall provide a written explanation of the specific grounds for its failure to completely and precisely respond. |
|
12/21/2018 4:34:41 PM
Read 1st, KPCOs application for approval of a contract for electric service to Braidy Industries Inc., including the direct testimony of Matthew J.Satterwhite, Ranie K. Wohnhas, and Alex E. Vaughan, KPCO"s motion for confidential treatment, and affidavit o Lerah Scott Kentucky Power Company |
|
12/14/2018 2:58:12 PM
20181214_PSC Acknowledgment Letter.pdf |
|
12/14/2018
Kentucky Power Company Notice of Intent to File an Application for Approval of a Contract for Electric Service with Braidy Industries Inc. Using Electronic Filing Procedures |