Kentucky Public Service Commission


View Case Filings for: 2016-00075


Case Number:2016-00075
Service Type:Water
Filing Date:2/26/2016
Category:Regular
Utilities:

Hardin County Water District #1


Case Nature:

APPLICATION OF HARDIN COUNTY WATER DISTRICT NO. 1 FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A WHOLESALE INTERCONNECT FACILITY TO THE LOUISVILLE WATER COMPANY









Case Filings
FilingDocuments
4/12/2016 9:32:53 AM

Final Order Entered: 1. Hardin District is granted a CPCN to proceed with the proposed construction as set forth in its application. 2. Hardin District shall notify the Commission prior to performing any additional construction not expressly authorized by this Order. 3. Any deviation from the approved construction shall be undertaken only with prior approval of Commission. 4. Hardin District shall require construction to be inspected under general supervision of a licensed professional engineer with a Kentucky registration in civil or mechanical engineering to ensure that construction work is done in accordance with contract drawings and specifications and in conformance with best practices of construction trades involved in the project. 5. Hardin District shall file documentation of total costs of project including cost of construction and all other capitalized costs, (e.g., engineering, legal, and administrative) within 60 days of the date that construction authorized under this CPCN is substantially completed. Construction costs shall be classified into appropriate plant accounts in accordance with the Uniform System of Accounts for water utilities prescribed by the Commission. 6. Hardin District shall file a copy of the "as-built" drawings and a certified statement that the construction has been satisfactorily completed in accordance with the contract plans and specifications within 60 days of the substantial completion of the construction certificated herein.


4/4/2016

Hardin County Water District No. 1 Response to Request for Information


3/29/2016 3:01:38 PM

Commission Staff's First Request for Information to Hardin County Water District No. 1


2/29/2016

Hardin County Water District No. 1 Filing of Updated Exhibit 7


2/26/2016 1:37:32 PM

Order Entered: 1 . Hardin No. 1's request for a deviation from the requirement of 807 KAR 5:001 , Section 7(1), regarding the filing of ten additional copies in paper medium for its application is granted. 2. Hardin No. 1, unless ordered otherwise, is permitted to hereafter file an original unbound and three additional copies in paper medium when filing a "paper," as the term is defined by 807 KAR 5:001, Section 1 (9), with the Commission in this proceeding. 3. Hardin No. 1's application in this case is accepted for filing as of the date of this Order.


2/10/2016 11:55:17 AM

Acknowledge Receipt of Filing


2/10/2016

Hardin County Water District No. 1 Request for Deviation


2/9/2016

Hardin County Water District No. 1 Project Manual


2/5/2016

Hardin County Water District No. 1 Application for a Certificate of Public Convenience and Necessity to Construct a Wholesale Interconnect Facility to the Louisville Water Company