Kentucky Public Service Commission


View Case Filings for: 2012-00564


Case Number:2012-00564
Service Type:Electric
Filing Date:2/11/2013
Category:Fuel Adjustment Clause
Utilities:

Jackson Energy Cooperative Corporation


Case Nature:

AN EXAMINATION OF THE APPLICATION OF THE FUEL ADJUSTMENT CLAUSE OF JACKSON ENERGY COOPERATIVE CORPORATION FROM NOVEMBER 1, 2010 THROUGH OCTOBER 31, 2012









Case Filings
FilingDocuments
5/17/2013 11:03:42 AM

Order Entered: 1. The charges and credits applied by Jackson Energy through the FAC for the period from November 1, 2010 through October 31, 2012 are approved. 2. Jackson Energy’s proposal to maintain its rates at their current level is approved.


4/8/2013

Jackson Energy Cooperative Corporation Affidavit of Mailing of Hearing Notice


3/12/2013

Jackson Energy Cooperative Response to Commissions Request for Information


2/13/2013

Affidavit of compliance of Jackson Purchase Energy


2/11/2013 1:02:23 PM

Order Entered: 1. A public hearing shall be held on April 9, 2013, at 10:00 a.m., Eastern Daylight Time, at the Commission’s offices in Frankfort, Kentucky, to examine the application of the Fuel Adjustment Clause of Jackson Energy Cooperative Corporation from November 1, 2010 through October 31, 2012. If no interested party files written notice with the Commission of its intent to attend this hearing by April 5, 2013, the public hearing shall be cancelled and the matter shall be considered submitted for decision based on the evidence in the record. 2. Jackson Energy shall file an affidavit with the Commission no later than 21 days from the date of this Order attesting to its compliance or noncompliance with the requirements of 807 KAR 5:056. 3. All documents that Jackson Energy with the Commission pursuant to 807 KAR 51056, Sections 1(7) and (9), during the period under review are incorporated by reference into the record of this proceeding. 4. Jackson Energy shall publish the following notice not less than 7 days or more than 21 days prior to the public hearing in a newspaper of general circulation in its service areas or in a trade publication or newsletter going to all customers. Jackson Energy shall also file an Affidavit of Publication of Hearing Notice with the Commission no later than April 5, 2013. 5. The official record of the proceeding shall be by video only.