APPLICATION OF SYMSONIA WATER DISTRICT FOR APPROVAL OF A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY FOR CONSTRUCTION OF WATER FACILITIES, FINANCING AND INCREASED RATES FOR WATER AND SEWER SERVICE









Case Filings
FilingDocuments
9/30/2013 3:06:54 PM

Order Entered: Commission HEREBY ORDERS, nunc pro tunc, that Appendix D to the Order of September 3, 2013 is stricken and the Appendix to this Order is substituted in its place.


9/3/2013 4:33:07 PM

Final Order Entered: 1. Symsonia District is granted a Certificate to proceed with the proposed construction project as set forth in its application. 2. Symsonia District shall notify the Commission prior to performing any additional construction not expressly authorized by this Order. 3. Any deviation from the construction approved shall be undertaken only with the approval of the Commission. 4. Symsonia District shall furnish documentation of the total costs of this project, including the cost of construction and all other capitalized costs (engineering, legal, administrative, etc.) within 60 days of the date that construction is substantially completed. Construction costs shall be classified into appropriate plant accounts in accordance with the Uniform System of Accounts for water utilities prescribed by the Commission. 5. Symsonia District shall file with the Commission a copy of the "as-built" drawings and a certified statement that the construction has been satisfactorily completed in accordance with the contract plans and specifications within 60 days of substantial completion of the construction certificated herein. 6. If any surplus from the budgeted funds remains upon completion of proposed project, Symsonia District shall advise Commission of this fact within 60 days of substantial completion of the construction. 7. If estimated total cost of is revised, Symsonia District shall within 10 days of revision file written notice of revised cost and reasons.


9/3/2013

Symsonia WD request for Final Order


7/11/2013

Symsonia Water District Signed Tariff Pages


7/1/2013

Symsonia Water District Notice of Intent to Implement Rate Increases


5/6/2013 2:37:35 PM

Order Entered: 1. The informal conference that is scheduled in this matter for May 8, 2013, is cancelled 2. No formal hearing will be conducted in this matter. 3. This matter stands submitted for decision.


4/11/2013

Symsonia Water District Response to Commission Order


4/4/2013 9:50:20 AM

Order Entered: 1. Symsonia Water District (“Symsonia District”) shall file with the Commission no later than April 15, 2013 written comments, if any, on the findings and recommendations contained in the Commission Staff Report and to request a hearing or a conference with Commission Staff in this matter. 2. Symsonia District’s failure to file with the Commission written objections to a finding or recommendation contained in the Commission Staff Report by April 15, 2013 shall be deemed as agreement and a waiver of any right to object to that finding or recommendation. 3. Symsonia District’s failure to request a formal hearing in this matter by April 15, 2013 shall be deemed a waiver of any right to a hearing in this matter. 4. If Symsonia District requests a hearing in this matter, it shall specifically identify in its written request for hearing all objections to the findings and recommendations set forth in the Commission Staff Report and shall provide a brief summary of testimony that it expects to present at hearing. 5. No later than April 15, 2013, Symsonia District shall file with the Commission, in writing, its position on: a. Adjusting its general rates for water service to a level that will produce $105,997 from water sales; b. Adjusting its general rates for sewer service to a level that will produce $122,598 from sewer sales; and, c. Changing the service lives of certain water and sewer assets to the service lives that Commission Staff has recommended.


4/1/2013 2:24:27 PM

Notice of Filing of Commission Staff Report


3/22/2013

Symsonia Water District Response to Commission Staffs Data Request


3/7/2013 12:25:47 PM

Commission Staff's First Request for Information to Symsonia Water District


3/5/2013 10:05:28 AM

Copy of memo to be admitted into the record concerning asset depreciation comments in regards to memo do within 5 days of receipt


1/29/2013 12:01:06 PM

Order Entered: 1) Symsonia District is granted leave to deviate from 807 KAR 5:001, Section 17(2)(a). 2) Symsonia District’s application is considered filed as of date of this Order. 3) Symsonia District’s notice of proposed rate adjustment is deemed effective as of date of this Order. 4) The rates set forth in Symsonia District’s application are suspended up to and including July 24, 2013. 5) The period for review of Symsonia District’s application for authorization to execute an Assistance Agreement with KIA is continued generally. 6) No later than April 1, 2013, Commission Staff shall file a written report containing its findings and recommendations regarding Symsonia District’s requested rate adjustment. 7) The parties shall file their written comments on and any objections to the findings and recommendations contained in the Commission Staff Report no later than April 15, 2013, or 14 days after the date of the filing of the Commission Staff Report, whichever occurs earlier. 8) A party’s failure to file written objections to a finding or recommendation contained in the Staff Report by April 30, 2013, or 14 days after the date of filing of Staff Report, whichever occurs earlier, shall be deemed as agreement with that finding or recommendation. 9) No later than April 30, 2013, or 14 days after the filing of the Staff Report, whichever occurs earlier, each party shall notify Commission whether matter may be submitted for decision based upon existing record without hearing.


12/14/2012

Symsonia Water District's Water Loss Report


12/12/2012 2:28:28 PM

Deficiency cured letter


12/7/2012

Symsonia Water District Response to Deficiency Letter


12/3/2012 3:24:54 PM

Deficiency letter


11/29/2012 2:00:09 PM

Acknowledge Receipt of Filing


11/29/2012

APPLICATION OF SYMSONIA WATER DISTRICT FOR APPROVAL OF A CERTIFICATE OF PUBLIC CONVENINECE AND NECESSITY FOR CONSTRUCTION OF WATER FACILITIES, FINANCING AND INCREASED RATES FOR WATER AND SEWER SERVICE