Kentucky Public Service Commission

Orders Orders RSS Feed Press Releases Press Releases RSS Feed
Follow @kypsc
Search PSC Site

View Case Filings for: 2018-00129


Case Number:2018-00129
Service Type:Electric
Filing Date:7/27/2018
Category:Regular
Utilities:

Inter-County Energy Cooperative Corporation



Case Nature:

APPLICATION OF INTER-COUNTY ENERGY COOPERATIVE CORPORATION FOR A GENERAL ADJUSTMENT OF EXISTING RATES



View Public Comments regarding this case






Case Filings
FilingDocuments
10/11/2018

Commission Staff's Notice of Informal Conference

PSC_IC_NOTICE

10/11/2018

Order Entered: 1. Inter-County Energy's motion for an extension of time is granted. 2. Inter-County Energy shall file its responses to Commission Staff's Fourth Request for Information on or before October 22, 2018.

PSC_ORDER

10/10/2018

Inter-County Energy Cooperative Corporation Motion for an Extension of Time

Inter-County Energy Cooperative Corporation Motion for an Extension of Time

10/8/2018

Commission Staff's Fourth Request for Information to Inter-County Energy Cooperative Corporation

DATA_REQUEST

9/11/2018

Inter-County Energy Cooperative Corporation Motion to Submit Case for Adjudication on the Record or, Alternatively, to Schedule a Hearing

Inter-County Energy Cooperative Corporation Motion to Submit Case for Adjudication

8/28/2018

Order Entered: 1. Inter-County Energy's motion for a deviation is granted in part and denied in part as discussed in detail above. 2. Inter-County Energy's application is accepted for filing as of July 27, 2018. 3. The proposed rates are suspended up to and including January 25, 2019. 4. All requests for intervention shall be filed no later than September 7, 2018. 5. The Commission's June 13, 2018 Order in this matter, including the procedural schedule, shall remain in full force and effect to the extent that it does not conflict with this Order.

PSC_ORDER

8/14/2018

Inter-County Energy Cooperative Corporation Response to Commission Staff Third Request for Information

Inter-County Energy Cooperative Corporation Response to Commission Staff Third Request for Information

8/14/2018

Inter-County Energy Cooperative Corporation Response to Commission Staff Third Request for Information

DR 2 13 - WP 1

8/14/2018

Inter-County Energy Cooperative Corporation Response to Commission Staff Third Request for Information

DR 2 17

8/14/2018

Inter-County Energy Cooperative Corporation Response to Commission Staff Third Request for Information

DR 2 19 post TY customer count

8/6/2018

Inter-County Energy Cooperative Corporation Affidavit of Publication

Inter-County Energy Cooperative Corporation Affidavit of Publication

7/31/2018

Commission Staff's Third Request for Information to Inter-County Energy Cooperative Corporation

DATA_REQUEST

7/18/2018

Inter-County Energy Cooperative Corporation Supplemental Response to Staffs First Request for Information, Item 34

Inter-County Energy Cooperative Corporation Supplemental Response to Staffs First Request for Information, Item 34

7/17/2018

Inter-County Energy Cooperative Corporation Response to Commission Staff Second Request for Information and Motion for Confidential Treatment

Inter-County Energy Cooperative Corporation Response to Commission Staff Second Request for Information and Motion for Confidential Treatment

7/13/2018

Inter-County Energy Cooperative Corporation Affidavit of Publication

Inter-County Energy Cooperative Corporation Affidavit of Publication

7/13/2018

Inter-County Energy Cooperative Corporation Motion for Deviation

Inter-County Energy Cooperative Corporation Motion for Deviation

7/3/2018

Commission Staff's Second Request for Information to Inter-County Energy Cooperative Corporation

DATA_REQUEST

6/19/2018

Inter-County Energy Cooperative Corporation Response to Staffs Initial Request for Information and Motion for Confidential Treatment

Inter-County Energy Cooperative Corporation Response to Staffs Initial Request for Information and Motion for Confidential Treatment

6/15/2018

Order Entered: 1. Inter-County's motion for an extension of time is granted. 2. Inter-County shall file its responses to Commission Staff's First Request for Information on or before June 19, 2018.

PSC_ORDER

6/13/2018

Order Entered: 1. Inter-County's proposed rates are suspended for five months from June 28, 2018, up to and including November 27, 2018. 2. The procedural schedule set forth in the Appendix to this Order shall be followed. 3. a. Responses to requests for information shall be appropriately bound, tabbed, and indexed and shall include the name of the witness responsible for responding to questions related to the information provided, with copies to all parties and an original and ten copies to the Commission. b. Each response shall be answered under oath or, for representatives of a public or private corporation or a partnership or an association or a governmental agency, be accompanied by a signed certification of the preparer or person supervising the preparation of the response on behalf of the entity that the response is true and accurate to the best of that person's knowledge, information, and belief formed after a reasonable inquiry. c. Any party shall make timely amendment to any prior response if it obtains information which indicates that the response was incorrect when made or, though correct when made, is now incorrect in any material respect. d. For any request to which a party fails or refuses to furnish all or part of the requested information , that party shall provide a written explanation of the specific grounds for its failure to completely and precisely respond.

PSC_ORDER

6/12/2018

Inter-County Energy Cooperative Corporation Motion for Extension of Time

Inter-County Energy Cooperative Corporation Motion for Extension of Time

6/1/2018

No deficiency letter

PSC No Deficiency Letter

5/29/2018

Acknowledge Receipt of Filing

PSC Acknowledgement Letter

5/29/2018

Inter-County Energy Cooperative Corporation Application for a General Adjustment of Existing Rates

Inter-County Energy Cooperative Corporation Application

5/4/2018

Commission Staff's First Request for Information to Inter-County Energy Cooperative Corporation

DATA_REQUEST

4/11/2018

Acknowledge Receipt of Filing

PSC Acknowledgment Letter

4/10/2018

Inter-County Energy Cooperative Corporation Notice of Intent to file an Application of General Adjustment of Existing Rates

Inter-County Energy Cooperative Corporation Notice of Intent