View Case Filings for: 2024-00343
Service Type:Electric
Filing Date:11/22/2024
Category:Regular
Utilities:
Kentucky Power Company
Electronic Case
Case Nature:
ELECTRONIC APPLICATION OF KENTUCKY POWER COMPANY FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO REPLACE AND UPGRADE PORTIONS OF THE BELLEFONTE STATION IN BOYD COUNTY, KENTUCKY (BELLEFONTE STATION UPGRADE PROJECT)
Case Filings | |
---|---|
Filing | Documents |
12/20/2024 2:04:58 PM
Kentucky Power Company’s Responses to Commission Staff’s First Set of Data Requests dated December 9, 2024 Marilyn Michelle Caldwell Kentucky Power Company |
|
12/19/2024 11:18:01 AM
Errata Direct Testimony of Daniel T. Barr and Errata Direct Testimony of Nicolas C. Koehler Marilyn Michelle Caldwell Kentucky Power Company |
|
12/9/2024 4:34:27 PM
COMMISSION STAFF’S FIRST REQUEST FOR INFORMATION TO KENTUCKY POWER COMPANY |
|
12/4/2024 8:59:33 AM
Order Entered: 1. Kentucky Power’s motion for an IC is granted. 2. The IC shall be December 17, 2024, at 10 a.m. Eastern Standard Time. Commission Staff shall facilitate arrangements. 3. The procedural schedule set forth in the Appendix to this Order shall be followed. 4. Kentucky Power shall respond to all requests for information propounded by Commission Staff, whether identified on the procedural schedule or otherwise, as provided in those requests. 5. Any party filing a paper with the Commission shall file an electronic copy in accordance with the electronic filing procedures set forth in 807 KAR 5:001, Section 8. Electronic documents shall be in portable document format (PDF), shall be searchable, and shall be appropriately bookmarked. The Commission directs the parties to the Commission’s July 22, 2021 Order in Case No. 2020-00085 regarding filings with the Commission. |
|
11/25/2024 4:17:47 PM
20241125_PSC Deficiency Cured Letter.pdf |
|
11/22/2024 4:29:37 PM
Kentucky Power Company’s Response To November 20, 2024 Deficiency Notice, Or In The Alternative, Request For Deviation Marilyn Michelle Caldwell Kentucky Power Company |
|
11/21/2024 3:50:32 PM
Kentucky Power Company’s Motion for Informal Conference Marilyn Michelle Caldwell Kentucky Power Company |
|
11/20/2024 4:07:37 PM
20241120_PSC Deficiency Letter.pdf |
|
11/15/2024 4:57:21 PM
Kentucky Power Company’s Application Marilyn Michelle Caldwell Kentucky Power Company |
|
10/22/2024 3:10:17 PM
20241022_PSC Acknowledgment Letter.pdf |
|
10/22/2024
Kentucky Power Company Notice of Intent to File an Application for a Certificate of Public Convenience and Necessity to Replace and Upgrade Portions of the Bellefonte Station in Boyd County, Kentucky Using Electronic Filing Procedures |