View Case Filings for: 2023-00421
Service Type:Electric
Filing Date:12/18/2023
Category:Regular
Utilities:
Kenergy Corp.
Case Nature:
Roger D. Shocklee, Complainant; Kenergy Corp., Defendant
Case Filings | |
---|---|
Filing | Documents |
1/10/2025 3:07:49 PM
Order Entered: 1. Mr. Shocklee’s motion for rehearing is granted in part. 2. Mr. Shocklee’s net metering applications may not be denied solely on the basis that he is a lessee of the property indicated in his applications. Kenergy may require Mr. Shocklee to submit a copy of his lease to establish his property rights prior to the application review requirements set out below. 3. Mr. Shocklee’s net metering applications may not be denied solely on the basis that that the sum of his proposed and existing facilities exceed the 45 kW capacity limit; however, the sum of facilities on a single meter may not exceed 45 kW capacity. 4. Mr. Shocklee’s complaint is denied because it seeks to establish that “Kenergy’s rejection of Complainant’s application for net metering service interconnection for review and processing (for approval or denial) was not based upon any claim of violation of any code, standard, or regulation related to reliability or safety” and Kenergy properly rejected Mr. Shocklee’s applications because the applications violated a standard related to reliability or safety. 5. Mr. Shocklee may submit a Level 2 application (tariff sheet 46R) and Kenergy shall comply with tariff sheet 46E requirements for review and notice. 6. The remainder of the December 4, 2024 Order not in conflict with this Order remains in effect. 7. This case is closed and removed from the Commission’s docket. |
|
1/6/2025
Kenergy Corp.'s Notice of Withdrawal of Counsel |
|
12/30/2024
Roger D. Shocklee Reply to Kenergy Corp. Response |
|
12/27/2024
Kenergy Corp. Response to Motion for Rehearing |
|
12/23/2024
Roger D. Shocklee Application for Rehearing |
|
12/4/2024 1:01:43 PM
Final Order Entered: 1. For the reasons set forth, the relief sought in Mr. Shocklee’s complaint is denied. 2. This case is closed and is removed from the Commission's docket. |
|
10/4/2024
|
|
10/4/2024
Kenergy Corp. Response to Commission Staff Second Request for Information |
|
9/27/2024 9:12:39 AM
COMMISSION STAFF’S SECOND REQUEST FOR INFORMATION TO KENERGY CORP. |
|
9/26/2024
Roger D. Shocklee Reply to Kenergy Corp. Response |
|
9/23/2024
Kenergy Response and Motion to Submit |
|
9/17/2024
Roger D. Shocklee Renewed Motion for Disposition |
|
3/14/2024
Kenergy Corp. Response to Commission First Request for Information and Motion for Confidential Treatment |
|
3/8/2024 12:32:22 PM
COMMISSION STAFF’S FIRST REQUEST FOR INFORMATION TO KENERGY CORP. |
|
2/27/2024
Roger D. Shocklee Reply to Kenergy Corp. Verified Response |
|
2/23/2024
Kenergy Corp. Response to Complainant Motion for Summary Disposition and Memorandum |
|
2/16/2024
Roger D. Shocklee Motion for Summary Disposition |
|
2/15/2024
Roger D. Shocklee Response to Commission Staff First Request for Information |
|
2/2/2024 2:10:15 PM
COMMISSION STAFF’S FIRST REQUEST FOR INFORMATION TO ROGER D. SHOCKLEE |
|
1/12/2024
Kenergy Corp. Answer to Complaint |
|
1/3/2024 1:58:26 PM
Order Entered: Kenergy shall satisfy the matters complained of or file a written answer to the complaint within ten days from the date of service of this Order. |
|
12/18/2023 1:51:20 PM
Acknowledge Receipt of Filing |
|
12/18/2023
Roger D. Shocklee v. Kenergy Corp. |