Kentucky Public Service Commission


View Case Filings for: 2023-00132


Case Number:2023-00132
Service Type:Water
Filing Date:4/26/2023
Category:Regular
Utilities:

Northern Kentucky Water District


Electronic Case
Case Nature:

ELECTRONIC APPLICATION OF NORTHERN KENTUCKY WATER DISTRICT FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY AND APPROVAL OF FINANCING FOR TAYLOR MILL TREATMENT PLANT EMERGENCY GENERATOR









Case Filings
FilingDocuments
6/30/2023 4:28:39 PM

Order Entered: 1. Northern Kentucky District’s motion for confidential treatment is granted. 2. The designated material granted confidential treatment by this Order shall not be placed in the public record or made available for public inspection for an indefinite period or until further Order of this Commission. 3. Use of the designated material granted confidential treatment by this Order in any Commission proceeding shall comply with 807 KAR 5:001, Section 13(9). 4. Northern Kentucky District shall inform the Commission if the designated material granted confidential treatment by this Order becomes publicly available or no longer qualifies for confidential treatment.


6/21/2023 2:38:36 PM

Final Order Entered: 1. Northern Kentucky District is granted a CPCN to construct the proposed project as set forth in the application. 2. Northern Kentucky District’s proposed plan of financing is approved. 3. Northern Kentucky District is authorized to use the remaining 4,065,000 of KIA Loan F20-044, and, under the terms of that Agreement, said amount is to be repaid over 20 years at an interest rate of 1.50 percent and an additional loan servicing fee of 0.25 percent. 4. The remaining proceeds from KIA Loan F20-044 shall be used only for the purposes specified in Northern Kentucky District’s application. 5. Northern Kentucky District shall obtain approval from the Commission prior to performing any additional construction not expressly approved by this Order. 6. Northern Kentucky District shall require construction to be inspected under general supervision of a licensed professional engineer with a Kentucky registration in civil or mechanical engineering to ensure that the construction work is done in accordance with the contract drawings and specifications and in conformance with best practices of the construction trades involved in the project.


6/5/2023 9:46:21 AM

Motion for Decision on the Record and Waiver of Hearing


Tom Edge Northern Kentucky Water District

5/26/2023 9:55:32 AM

Response to Commission Staffs First Request for Information


Tom Edge Northern Kentucky Water District

Response_to_Commission_Staffs_First_Request_for_Information.pdf

Response to Commission Staff's First Request for Information

5/18/2023 11:47:10 AM

Order Entered: 1. Northern Kentucky District’s application for approval of the proposed evidence of indebtedness is continued beyond the 60-day period specified in KRS 278.300(2). 2. The procedural schedule set forth in Appendix A to this Order shall be followed. 3. Northern Kentucky District shall respond to all requests for information propounded by Commission Staff, whether identified on the procedural schedule or otherwise, as provided in those requests.


4/27/2023 9:47:41 AM

20230427_PSC No Deficiency Letter.pdf


4/26/2023 2:13:11 PM

Application and Motion for Confidentiality


Tom Edge Northern Kentucky Water District

Application_and_Exhibits.pdf

Application and Exhibits

Motion_for_Confidentiality.pdf

Motion for Confidentiality

4/19/2023 11:48:15 AM

20230419_PSC Acknowledgment Letter.pdf


4/19/2023

Northern Kentucky Water District Notice of Intent to File an Application for a Certificate of Public Convenience and Necessity and Approval of Financing for Taylor Mill Treatment Plant Emergency Generator Using Electronic Filing Procedures


20230419_Northern Kentucky Water District Notice of Intent and Election.pdf

Northern Kentucky Water District Notice of Intent and Election