Kentucky Public Service Commission


View Case Filings for: 2023-00011


Case Number:2023-00011
Service Type:Electric
Filing Date:9/6/2023
Category:Fuel Adjustment Clause
Utilities:

Louisville Gas and Electric Company


Electronic Case
Case Nature:

AN ELECTRONIC EXAMINATION OF THE APPLICATION OF THE FUEL ADJUSTMENT CLAUSE OF LOUISVILLE GAS & ELECTRIC COMPANY FROM NOVEMBER 1, 2020 THROUGH OCTOBER 31, 2022









Case Filings
FilingDocuments
5/6/2024 5:58:42 PM

Final Order Entered: 1. The charges and credits applied by LG&E through the FAC for the period from November 1, 2020, through October 31, 2022, are approved. 2. LG&E's proposed base fuel cost of $0.02860 per kWh is approved. 3. Beginning with the expense month of June 2024, LG&E shall use an FAC rate based upon a base fuel cost of $0.02860 per kWh. 4. LG&E shall increase its base energy rates by $0.00512 per kWh for service rendered on and after June 1, 2024, to reflect the increase of $0.00512 per kWh to LG&E’s base fuel cost, which is the differential between the old base fuel cost of $0.02348 per kWh and the new base fuel cost of $0.02860 per kWh. 5. Within 20 days of the date of this Order, LG&E shall file, using the Commission's electronic Tariff Filing System, its revised tariff sheets with the Commission setting out the increase in its base energy rates discussed herein and reflecting that they were approved pursuant to this Order. 6. This case is closed and removed from the Commission's docket.


5/6/2024 5:19:28 PM

Order Entered: 1. The charges and credits billed by LG&E through its FAC from May 1, 2021, through October 31, 2021, are approved. 2. The charges and credits billed by LG&E through its FAC from November 1, 2021, through April 30, 2022, are approved. 3. A copy of this Order shall be entered into the record in Case Nos. 2022-00039 and 2022-00266.


2/29/2024 12:39:49 PM

20240229_PSC Notice of Filing Hearing Documents - January 4, 2024.pdf


1/3/2024 4:45:43 PM

LGEs Affidavit of Publications of Hearing Notice and Petition for Approval to Deviate from Rule


Andrea M. Fackler Louisville Gas and Electric Company

1_-_Read_1st_1-3-2024_(CN_2023-00011).pdf

LG&E Read 1st 1-3-2024 (CN 2023-00011)

2_-_LGE_Affidavit_of_Publications_(CN_2023-00011).pdf

LG&E Affidavit of Publications (CN 2023-00011)

3_-_LGE_Petition_for_Approval_to_Deviate_(CN_2023-00011).pdf

LG&E Petition for Approval to Deviate from Rule (CN 2023-00011)

12/21/2023 9:13:58 AM

Order Entered: 1. LG&E’s motion to allow Charles R. Schram, Director – Energy Planning, to adopt the pre-filed direct testimony of, and data responses sponsored by, Stuart A. Wilson, Director – Energy Planning, Analysis and Forecasting at the January 4, 2024 hearing is granted. 2. Mr. Wilson is excused from the January 4, 2024 hearing.


12/20/2023 2:54:06 PM

Order Entered: 1. LG&E’s September 22, 2023 petition for confidential treatment is granted. 2. The designated material granted confidential treatment by this Order shall not be placed in the public record or made available for public inspection for five years or until further order of this Commission. 3. Use of the designated material granted confidential treatment by this Order in any Commission proceeding shall comply with 807 KAR 5:001, Section 13(9). 4. LG&E shall inform the Commission if the designated material granted confidential treatment by this Order becomes publicly available or no longer qualifies for confidential treatment. 5. If a nonparty to this proceeding requests to inspect the material granted confidential treatment by this Order and the period during which the material has been granted confidential treatment has not expired, LG&E shall have 30 days from receipt of written notice of the request to demonstrate that the material still falls within the exclusions from disclosure requirements established in KRS 61.878. If LG&E is unable to make such demonstration, the requested material shall be made available for inspection. Otherwise, the Commission shall deny the request for inspection. 6. The Commission shall not make the requested material available for inspection for 30 days from the date of service of an Order finding that the material no longer qualifies for confidential treatment in order to allow LG&E to seek a remedy afforded by law.


11/29/2023 10:54:19 AM

LGE and KU Motion to Adopt Data Responses and Testimony


Andrea M. Fackler Louisville Gas and Electric Company

1_-_Read_1st_11-29-2023_(CN_2023-00010_2023-00011).pdf

Read 1st 11-29-2023 (CN 2023-00010 and CN 2023-00011)

2_-_KU_and_LGE_Motion_to_Adopt_Testimony_(CN_2023-00010_2023-00011).pdf

LG&E and KU Motion to Adopt Data Responses and Testimony (CN 2023-00010 and CN 2023-00011)

11/27/2023 2:58:59 PM

LGE Updated Hearing Notice Preparation Documents


Andrea M. Fackler Louisville Gas and Electric Company

1_-_Read_1st_11-27-2023_(CN_2023-00011).pdf

Read 1st 11-27-2023 (CN 2023-00011)

2_-_LGE_Revised_Request_to_KY_Press_to_Publish_Hearing_Notice_(CN_2023-00011).pdf

LG&E Revised Request to KY Press to Publish Hearing Notice (CN 2023-00011)

11/21/2023 3:50:42 PM

LGEs Hearing Notice Preparation Documents


Andrea M. Fackler Louisville Gas and Electric Company

1_-_Read_1st_11-21-2023_(CN_2023-00011).pdf

Read 1st Filing Letter - 11-21-2023 (CN 2023-00011)

2_-_LGE_Request_to_KY_Press_to_Publish_Hearing_Notice_(CN_2023-00011).pdf

LG&E Request to KY Press to Publish Hearing Notice (CN 2023-00011)

11/20/2023 1:34:04 PM

Order Entered: 1. A hearing in this matter shall be held on January 4, 2024, at 9 a.m. Eastern Standard Time and continuing until called from the bench by the presiding officer, in the Richard Raff Hearing Room at the offices of the Public Service Commission at 211 Sower Boulevard, Frankfort, Kentucky. 2. Pursuant to 807 KAR 5:001, Section 2, if the hearing is not concluded on the designated day, the hearing may be continued upon verbal announcement by the presiding officer. A verbal announcement made by the presiding officer shall be proper notice of the continued hearing. 3. Witnesses who sponsor schedules, testimony, or responses to requests for information shall participate in person at the January 4, 2024 hearing. 4. Louisville Gas and Electric Company (LG&E) shall give notice of the hearing in compliance with 807 KAR 5:001, Section 9(2)(b).


10/20/2023 10:14:22 AM

Louisville Gas and Electric Companys Responses to the Commission Staffs Second Request for Information


Andrea M. Fackler Louisville Gas and Electric Company

1_-_Read_1st_10-20-2023_(CN_2023-00011).pdf

Read 1st 10-20-2023 (CN 2023-00011)

2_-_LGE_Responses_to_PSC_Second_Data_Request_(CN_2023-00011).pdf

LG&E Responses to the Commission Staff's Second Request for Information (CN 2023-00011)

10/5/2023 1:26:43 PM

Data Request


9/22/2023 5:00:47 PM

LGE Direct Testimonies and Responses to Information Requested In Appendix B of the Commissions Order dated September 6, 2023


Andrea M. Fackler Louisville Gas and Electric Company

1_-_Read_1st_09-22-2023_(CN_2023-00011).pdf

Read 1st 9-22-2023 (CN 2023-00011)

2_-_LGE_Petition_for_Confidential_Protection_(CN_2023-00011).pdf

LG&E Petition for Confidential Protection (CN 2023-00011)

4_-_LGE_PSC_DR1_Data_Responses_(CN_2023-00011).pdf

LG&E PSC DR1 Data Responses (CN 2023-00011)

5_-_LGE_PSC_DR1_Excel_Attachment_to_Response_to_Question_No._17_(CN_2023-00011).xlsx

LG&E PSC DR1 Excel Attachment to Response to Q17 (CN 2023-00011)

9/7/2023 1:05:19 PM

Written Statement in Response to Ordering Paragraph 5 in the Commissions September 6, 2023 Order


Andrea M. Fackler Louisville Gas and Electric Company

2_-_LGE_FAC_Written_Statement_CN_2023-00011.pdf

LG&E FAC Review Written Statement

9/6/2023 9:29:35 AM

Order Entered: 1. The procedural schedule set forth in Appendix A to this Order shall be followed. 2. On or before the date set forth in the procedural schedule, LG&E shall file its responses to the Commission Staff’s request for information, attached to this Order as Appendix B. 3. LG&E shall respond to any additional requests for information propounded by Commission Staff as provided in those requests. 4. LG&E shall file with the Commission, no later than the date set forth in the procedural schedule attached as Appendix A, written direct testimony of the witnesses LG&E intends to call at the scheduled hearing in this matter.