View Case Filings for: 2022-00065
Service Type:Water
Filing Date:4/5/2022
Category:Regular
Utilities:
South Eastern Water Association, Inc.
Electronic Case
Case Nature:
ELECTRONIC APPLICATION OF SOUTH EASTERN WATER ASSOCIATION, INC. FOR COMMISSION APPROVAL PURSUANT TO 807 KAR 5:001 AND KRS 278.020 FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A CUSTOMER SERVICE AND OPERATIONS FACILITY
Case Filings | |
---|---|
Filing | Documents |
8/30/2022 1:22:50 PM
Final Order Entered: 1. South Eastern Water’s request for a CPCN for the proposed projects described in its application is granted. 2. South Eastern Water shall immediately notify the Commission upon knowledge of any material changes to the project, including, but not limited to, a material increase in costs and any significant delays in construction. 3. Any material deviation from the construction approved by this Order shall be undertaken only with the prior approval of the Commission. 4. South Eastern Water shall file with the Commission documentation of the total costs of the projects, including the cost of construction and all other capitalized costs, (e.g. engineering, legal, administrative, etc.) within 60 days of the date that construction authorized under this CPCN is substantially completed. Construction costs shall be classified into appropriate plant accounts in accordance with the Uniform System of Accounts for electric utilities as prescribed by the Commission. 5. South Eastern Water shall file a copy of the “as-built” drawings, if any, and a certified statement that the construction has been satisfactorily completed in accordance with the plans and specifications within 60 days of the substantial completion of the construction certificated herein. 6. Any documents filed in the future pursuant to ordering paragraph 2 through 5 shall reference this case number and shall be retained in the utility’s general correspondence files. |
|
7/5/2022 5:06:44 AM
Notice of Submission Felisa S. Moore South Eastern Water Association Inc. |
|
6/27/2022 4:32:01 PM
Response of South Eastern Water Association Inc. to Commission Staffs Second Request for Information Felisa S. Moore South Eastern Water Association Inc. |
|
6/14/2022 2:08:09 PM
Data Request |
|
5/26/2022 10:11:59 PM
SEWAs Response to Commission Staff’s First Request for Information Felisa S. Moore South Eastern Water Association Inc. |
|
5/11/2022 10:01:48 AM
Data Request |
|
4/22/2022 3:52:58 PM
Order Entered: 1. The procedural schedule set forth in the Appendix to this Order shall be followed. 2. Any party filing a paper copy with the Commission shall file an electronic copy in accordance with the electronic filing procedures set forth in 807 KAR 5:001, Section 8. Electronic documents shall be in portable document format (PDF), shall be searchable, and shall be appropriately bookmarked. |
|
4/7/2022 12:27:41 PM
20220407_PSC Deficiency Cured Letter.pdf |
|
4/5/2022 3:52:38 PM
Amended application of South Eastern Water Association, Inc. Damon R. Talley South Eastern Water Association, Inc. |
|
4/4/2022 11:10:40 AM
20220404_PSC Deficiency Letter.pdf |
|
3/29/2022 5:23:46 PM
Application of South Eastern Water Association, Inc. for a Certificate of Public Convenience and Necessity to construct a customer service and operations facility. Damon R. Talley South Eastern Water Association, Inc. |
|
3/1/2022 10:14:07 AM
20220301_PSC Acknowledgment Letter.pdf |
|
3/1/2022
South Eastern Water Association, Inc. Notice of Intent to File an Application for a Certificate of Public Convenience and Necessity to Construct an Office Building Using Electronic Filing Procedures |