View Case Filings for: 2020-00119
Service Type:Water
Filing Date:4/14/2020
Category:Regular
Utilities:
Western Pulaski County Water District
Electronic Case
Case Nature:
ELECTRONIC APPLICATION OF WESTERN PULASKI COUNTY WATER DISTRICT FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A WATER IMPROVEMENTS PROJECT PURSUANT TO KRS 278.020 AND KAR 5:001
Case Filings | |
---|---|
Filing | Documents |
7/28/2021 10:46:29 AM
Order Entered: 1. Western Pulaski District’s motion for an extension of time is denied. 2. Western Pulaski District shall file an application for a general rate adjustment pursuant to 807 KAR 5:001, Section 16, or an application for an alternative rate adjustment pursuant to 807 KAR 5:076 by December 17, 2021. 3. This case is closed and removed from the Commission’s docket. |
|
7/2/2020 12:09:51 PM
Final Order Entered: 1. Western Pulaski District is granted a CPCN to construct the proposed project as set forth in the Amended Application. 2. Western Pulaski District shall obtain approval from the Commission prior to performing any additional construction not expressly approved by this Order. 3. Western Pulaski District shall require construction to be inspected under general supervision of a licensed professional engineer with a Kentucky registration in civil or mechanical engineering to ensure that the construction work is done in accordance with the contract drawings and specifications and in conformance with best practices of the construction trades involved in the project. 4. Western Pulaski District shall file with the Commission documentation of the total cost of the project within 60 days of the date that construction authorized under this CPCN is substantially completed. Construction costs shall be classified into the appropriate plant accounts in accordance with the Uniform System of Accounts for water utilities prescribed by the Commission. 5. Western Pulaski District shall file a copy of the "as-built" drawings and a certified statement that the construction has been satisfactorily completed in accordance with the contract plans and specifications within 60 days of the substantial completion of the construction authorized under this CPCN. |
|
6/2/2020 3:32:18 PM
Supplemental Response W. Randall Jones Western Pulaski County Water District |
|
5/22/2020 4:00:58 PM
Amended Application W. Randall Jones Western Pulaski County Water District |
|
5/22/2020 10:53:18 AM
Supplemental Response W. Randall Jones Western Pulaski County Water District |
|
5/19/2020 1:53:11 PM
Response W. Randall Jones Western Pulaski County Water District |
|
5/13/2020 7:47:58 AM
Data Request |
|
5/7/2020 11:17:16 AM
Response to Information Request W. Randall Jones Western Pulaski County Water District |
|
4/21/2020 10:47:29 AM
Data Request |
|
4/15/2020 1:44:07 PM
20200415_PSC No Deficiency Letter.pdf |
|
4/14/2020 3:16:01 PM
Application and Supporting Documents W. Randall Jones Western Pulaski County Water District |
|
4/6/2020 9:33:43 AM
20200406_PSC Acknowledgment Letter.pdf |
|
4/6/2020
Western Pulaski County Water District Notice of Intent to File an Application for a Certificate of Public Convenience and Necessity to Construct a System Improvements Project pursuant to KRS 278.020 Using Electronic Filing Procedures |