Case Nature:

AN EXAMINATION BY THE PUBLIC SERVICE COMMISSION OF THE ENVIRONMENTAL SURCHARGE MECHANISM OF BIG RIVERS ELECTRIC CORPORATION FOR THE SIX-MONTH BILLING PERIOD ENDING JANUARY 31, 2018, AND THE PASS THROUGH MECHANISM OF ITS THREE MEMBER DISTRIBUTION COOPERATIVES









Case Filings
FilingDocuments
9/24/2018 2:38:08 PM

Final Order Entered: 1. The amounts billed by BREC through its environmental surcharge for the period August 1, 2017, through January 31, 2018, are approved. 2. The amounts billed by Jackson Purchase and Kenergy through their respective environmental surcharge pass-through mechanisms for the period August 1, 2017, through January 31, 2018, for all customers with dedicated delivery points are approved. 3. The amounts billed by the three Member Cooperatives through their respective environmental surcharge pass-through mechanisms for the period September 1, 2017, through February 28, 2018, for all non-dedicated delivery point customers are approved. 4. The rates of return determined by BREC for each month of the review period are approved. 5. This case is closed and removed from the Commission's docket.


9/4/2018

Big Rivers Electric Corporation Request to Submit Matter for Adjudication


7/6/2018

Big Rivers Electric Corporation Direct Testimony of Nicolas R. Castlen and Response to Commission Staff First Request for Information


6/13/2018 1:47:42 PM

Order Entered: 1. Big Rivers and each of its three Member Cooperatives listed in footnote 2 shall be made parties to this case. 2. The procedural schedule set forth in Appendix A to this Order shall be followed in this proceeding. 3. Any motion to intervene filed after the date set forth in Appendix A shall show a basis for intervention and good cause tor being untimely. If the untimely motion is granted, the movant shall accept and abide by the existing procedural schedule. 4. By the date set forth in Appendix A, Big Rivers shall file its prepared direct testimony in support of the reasonableness of the application of its environmental surcharge mechanism and the three Member Cooperatives, or Big Rivers on their behalf, shall file by that date their prepared direct testimony in support of the reasonableness of the application of the pass-through mechanism during the periods under review. 5. Any party filing testimony shall file an original and six copies. 6. a. The information requested herein is due on or before the date specified in Appendix A to this Order. Responses to requests for information shall be appropriately bound, tabbed, and indexed and shall include the name of the witness responsible for responding to the questions related to the information provided, with copies to all parties of record and six copies to the Commission.