View Case Filings for: 2015-00324
Service Type:Water
Filing Date:10/13/2015
Category:Regular
Utilities:
Northern Kentucky Water District
Electronic Case
Case Nature:
APPLICATION OF NORTHERN KENTUCKY WATER DISTRICT FOR APPROVAL OF MADISON PIKE 24 INCH HYDRAULIC REDUNDANCY PROJECT (PHASE 1) FOR ISSUANCE OF A CERTIFICATE OF CONVENIENCE AND NECESSITY
Case Filings | |
---|---|
Filing | Documents |
11/23/2015 2:24:54 PM
Order Entered: Northern District is granted a CPCN to proceed with the proposed construction as set forth in its application. 2. Northern District shall notify the Commission prior to performing any additional construction not expressly authorized by this Order. 3. Any deviation from the construction approved shall be undertaken only with the prior approval of the Commission. 4. Northern District shall require construction to be inspected under the general supervision of a licensed professional engineer with a Kentucky registration in civil or mechanical engineering to ensure that the construction work is done in accordance with the contract drawings and specifications and in conformance with the best practices of the construction trades involved in the project. Northern District shall submit an application to the Commission prior to issuing any securities that require approval pursuant to KRS 278.300. 6. Northern District shall file with the Commission documentation of the total costs of this project, including the cost of construction and all other capitalized costs, (e.g., engineering, legal, administrative) within 60 days of the date that construction authorized under this CPCN is substantially completed. Construction costs shall be classified into appropriate plant accounts in accordance with the Uniform System of Accounts for water utilities prescribed by the Commission. 7. Northern District shall file a copy of the "as-built" drawings and a certified |
|
10/26/2015 2:58:25 PM
20151026_PSC Deficiency Cured Letter.pdf |
|
10/13/2015 2:11:19 PM
Deficiency Response Lindsey Rechtin |
|
10/13/2015 9:24:16 AM
20151013_PSC_Deficiency Letter.pdf |
|
10/8/2015 9:40:30 AM
Confidentiality Petition Lindsey Rechtin |
|
10/2/2015 2:39:49 PM
Application for Certificate of Convenience and Necessity Lindsey Rechtin |
|
9/28/2015 8:41:08 AM
20150928_PSC_Acknowledgement Letter.pdf |
|
9/24/2015
Northern Kentucky Water District Notice of Intent to File Application for a Certificate of Convenience and Necessity |