Kentucky Public Service Commission


View Case Filings for: 2014-00458


Case Number:2014-00458
Service Type:Electric
Filing Date:2/5/2015
Category:Fuel Adjustment Clause
Utilities:

Clark Energy Cooperative, Inc.


Case Nature:

AN EXAMINATION OF THE APPLICATION OF THE FUEL ADJUSTMENT CLAUSE OF CLARK ENERGY COOPERATIVE, INC. FROM NOVEMBER 1, 2012 THROUGH OCTOBER 31, 2014









Case Filings
FilingDocuments
8/11/2015 10:05:00 AM

Order Entered: The charges and credits applied by Clark through the FAC for the period from November 1, 2012, through October 31, 2014, are approved. 2. Clark's proposal to maintain its rates at their current level is approved.


5/8/2015

Clark Energy Coop. Inc. Affidavit of Mailing


3/3/2015

Clark Energy Response to Order


2/16/2015

Clark Energy affidavit


2/5/2015 2:22:59 PM

Order Entered: 1. A public hearing shall be held on April 7, 2015, at 10:00 a.m., Eastern Daylight Time, at the Commission's offices in Frankfort, Kentucky, to examine the application of the Fuel Adjustment Clause of Clark from November 1, 2012, through October 31, 2014. If no interested party files written notice with the Commission of its intent to attend this hearing by April 3, 2015, the public hearing shall be cancelled and the matter shall be considered submitted for decision based on the evidence in the record. 2. Clark shall file an affidavit with the Commission no later than 21 days from the date of this Order attesting to its compliance or noncompliance with the requirements of 807 KAR 5:056. 3. All documents that Clark filed with the Commission pursuant to 807 KAR 5:056, Sections 1(7) and (9), during the period under review are incorporated by reference into the record of this proceeding. 4. Clark shall publish the following notice not less than seven days or more than 21 days prior to the public hearing in a newspaper of general circulation in its service areas or in a trade publication or newsletter going to all customers. Clark shall also file an Affidavit of Publication of Hearing Notice with the Commission no later than April 3, 2015. 5. The official record of the proceeding shall be by video only.