View Case Filings for: 2014-00086
Service Type:Water
Filing Date:5/2/2014
Category:Regular
Utilities:
Todd County Water District
Case Nature:
APPLICATION OF TODD COUNTY WATER DISTRICT FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT AN OFFICE BUILDING AND WAREHOUSE FACILITY
Case Filings | |
---|---|
Filing | Documents |
7/1/2014 3:15:01 PM
Order Entered: Todd District is granted a CPCN to proceed with the proposed construction as set forth in its application. 2. Todd District shall notify the Commission prior to performing any additional construction not expressly authorized by this Order. 3. Any deviation from the construction approved shall be undertaken only with prior approval of the Commission. Todd District shall file with the Commission documentation of the total costs of this project, including construction and all other capitalized costs (engineering, legal, administrative, etc.), within 60 days of the date that construction is substantially completed. Construction costs shall be classified into appropriate plant accounts in accordance with the Uniform System of Accounts for water utilities prescribed by the Commission. 5. Todd District shall file a copy of the "as-built" drawings and a certified statement that the construction has been satisfactorily completed in accordance with the contract plans and specifications within 60 days of the substantial completion of the construction certificated herein. 6. The proposed project shall be subject to all state and local building requirements. 7. Todd District shall file copies of permits related to the new construction herein within 30 days of obtaining such permits. 8. Todd District shall file a copy of the executed agreement with the winning bidder within 20 days of its execution. 8. Any documents filed in the future pursuant to orderi |
|
6/13/2014
Todd County Water District Response and Notice |
|
6/10/2014 3:14:10 PM
Order Entered: Todd County Water District shall show cause in writing, no later than seven days from the issuance of this Order, why it failed to comply with the Commission's May 15, 2014 Order, or in the alternative, shall file with the Commission the information requested in Commission Staff's First Request for Information. |
|
5/15/2014 10:35:51 AM
Commission Staff's First Request for Information to Todd County Water District |
|
5/14/2014 3:16:02 PM
Letter Revising Case Caption |
|
5/5/2014 9:02:25 AM
Deficiency cured letter |
|
5/2/2014
Todd County Water District Third Supplement to the Application for CPCN |
|
5/1/2014 10:19:22 AM
Still Deficient Letter |
|
4/14/2014
Toddy County Water District Second Supplement to Application for Certificate of Convenience and Necessity |
|
4/9/2014 9:38:28 AM
Still Deficient Letter |
|
4/1/2014
Todd County Water District's Amendment to Supplemental Filing |
|
3/31/2014
Todd County Water District's Supplement to the Application for Certificate of Convenience and Necessity |
|
3/18/2014 3:42:25 PM
Deficiency letter, information due 3/28 |
|
2/6/2014
Todd County Water District Application for a CPC&N to Construct and Office Building in Warehouse Facility Premises |