View Case Filings for: 2013-00251
Service Type:Water
Filing Date:7/3/2013
Category:Regular
Utilities:
Hardin County Water District #1 , Louisville Water Company
Case Nature:
INVESTIGATION INTO THE PROPOSED WATER PURCHASE AGREEMENT BETWEEN LOUISVILLE WATER COMPANY AND HARDIN COUNTY WATER DISTRICT NO. 1
Case Filings | |
---|---|
Filing | Documents |
9/12/2014 1:39:11 PM
Order Entered: Contracts and amendments to contracts for the sale for resale of water by a city-owned utility to a Commission-regulated water utility shall be filed by the seller with the Commission pursuant to KRS 278.200, but the Commission-regulated water utility need not obtain approval as an evidence of indebtedness under KRS 278.300 of any minimum purchase requirement in such a contract or amendment. 2. In the future, when Hardin District No 1 enters into a contract with a city owned water utility that requires Hardin District No. 1 to apply for a Certificate of Public Convenience and Necessity, Hardin District No. 1 shall file with the Commission the contract for approval along with the application for a Certificate of Public Convenience and Necessity. 3. Except for the provision of an SDC, all other provisions of the contract dated May 15, 2012 between Louisville Water and Hardin District No. 1 are approved contingent on Hardin District No. 1's filing of an application for a Certificate of Public Convenience and Necessity and the Commission's granting of the Certificate of Public Convenience and Necessity. 4. Any request to impose an SDC shall be filed in an application as required by 807 KAR 5:090 and shall be charged only after approval by the Commission. 5. Hardin District No. 1 shall file an application for a Certificate of Public Convenience and Necessity prior to commencing construction along Dixie Highway of a $4.5 million water project to c |
|
7/29/2014 10:07:02 AM
Memorandum dated 7/29/14 for Informal Conference of 7/17/14; Comments, if any, due 8/5/14 |
|
6/10/2014 9:59:21 AM
Commission Staff's Renotice of Informal Conference |
|
6/2/2014 3:17:35 PM
COMMISSION STAFF'S NOTICE OF INFORMAL CONFERENCE |
|
8/21/2013
Hardin County Water District #1 Response to Commission Order Dated July 3, 2013 |
|
8/19/2013
Louisville Water Company's Response to Commission Order dated July 3, 2013 |
|
8/2/2013 2:39:47 PM
Order Entered: that the Movants’ Joint Motion for Extension of Time is granted and that they shall have until August 17, 2013 to file their written memorandum. |
|
7/31/2013
Joint Motion for Extension of Time to File Written Memorandums |
|
7/3/2013 3:50:50 PM
Order Entered: (1) This proceeding is established to investigate the reasonableness and lawfulness of the proposed water purchase agreement between Louisville Water Company and Hard in District. (2) Louisville Water Company and Hardin District are made parties to this proceeding. (3) Within 30 days of the date of this Order, Louisville Water Company and Hardin District shall file with the Commission a written memorandum addressing whether KRS 278.300(1) requires Hardin District to apply for Commission approval prior to executing the proposed water purchase agreement. (4) Hardin District shall take no action to implement the provisions of the proposed water purchase agreement until completion of this proceeding without express Commission approval. |
|
6/13/2012
Hardin County Water District No. 1 Wholesale Water Purchase Agreement with Louisville Water Company |