FilingDocuments
1/25/2011 3:48:48 PM

Order Entered: 1. The conditional approval granted in our December 22, 2010 Order for Duke Kentucky to transfer its transmission assets to PJM is now unconditional. 2. Within 90 days of the date of this Order, Duke Kentucky shall file its internal procedures for the receipt and tracking of notices from PJM regarding customer requests to participate in PJM demand-response programs. Those procedures shall be reviewed by the Commission on an informal basis, unless a determination is made that a formal investigation is needed 3. Any document filed in the future pursuant to Ordering paragraph 2 herein, shall reference this case number and shall be retained in the utility’s general correspondence file.


1/6/2011 4:15:37 PM

Order Entered: IT IS THEREFORE ORDERED that the conditional approval granted in our December 22, 2010 Order has not become unconditional and will not become unconditional until either: (a) PJM clarifies its December 29, 2010 letter to acknowledge the requirement that no customer participate in a PJM demand-response program absent prior Commission approval; or (b) the December 22, 2010 Order is modified in response to a timely application for rehearing filed pursuant to KRS 278.400.


12/22/2010 3:42:04 PM

Final Order Entered: (1) Duke Kentucky's request to transfer functional control of its transmission system from the Midwest ISO to PJM is approved subject to filing, within seven days of the date of this Order, of the written acknowledgements described in finding paragraphs 8 and 9 above. (2) Any customer seeking to participate directly or through a third party in any PJM demand-response program shall do so only in accordance with the procedures set forth in finding paragraph 6 above. (3) Within 20 days of the date of this Order, Duke Kentucky shall file its revised tariff Rider PSM as approved herein with an effective date of January 1, 2012.


12/14/2010 2:45:54 PM

Order Entered: (1) The Midwest ISO's motion for an extension of time to file its post-hearing brief is granted. (2) Duke Kentucky's motion to strike the Midwest ISO's brief in its entirety or to strike three arguments in that brief, is denied.


12/14/2010 2:26:05 PM

Letter to Rocco O. D'Ascenzo granting Duke's petition for confidentiality filed 10/28/10 for protection of certain information


12/14/2010 2:24:50 PM

Letter to Rocco O. D'Ascenzo granting Duke's petition for confidentiality filed 11/19/10 for protection of certain information


12/14/2010 2:23:26 PM

Letter to Keith L. Beall and Rocco O. D'Ascenzo granting Duke's petition for confidentiality filed 11/22/10 for protection of certain information


12/1/2010

MISO's Response to Duke's Memorandum Contra and Motion to Strike


11/24/2010

Duke Energy's Memorandum Contra of MISO's Motion for Extension of Time (fax)


11/24/2010

Duke Energy's Memorandum Contra of MISO's Motion for Extension of Time


11/22/2010

MISO's Post-Hearing Brief


11/22/2010

MISO’s Motion for Extension of Time to File Post-Hearing Brief


11/22/2010

MISO's Petition for Confidential Treatment for Supplement to Post-Hearing Brief


11/19/2010

Duke Energy's Public Post Hearing Brief with Confidential Petition


11/19/2010

PJM Interconnection, LLC's Post Hearing Brief


11/10/2010 3:02:46 PM

Letter to Rocco D'Ascenzo granting Duke Energy Kentucky, Inc.'s petition for confidentiality filed 9/28/10 for protection of certain information


11/10/2010

Duke Energy's Responses to MISO's Post-Hearing Data Requests


11/8/2010 12:59:33 PM

Notice of Filing


11/3/2010 10:10:46 AM

Order Entered: (1) MISO's motion to take administrative notice of filings made by the parties and the Commission in FERC Docket No. ER10-1562-000 is denied without prejudice. (2) MISO's motion to compel Duke Kentucky to more fully respond to MISO's second set of data requests is denied as moot.


10/28/2010

Duke Energy's Response to MISO's 2nd Set of Clarifying Data Requests and Confidential Petition


10/28/2010


10/27/2010

Duke Energy's Letter in Response to MISO's Second Set of Data Requests with Confidential CD


10/26/2010

Duke Energy's Notice and Affidavit of Publication of Hearing


10/21/2010


10/18/2010

Duke Energy's Revised Response to MISO-DR-02-005 and 012


10/18/2010

Duke Energy's Revised Response to MISO-DR-02-005 and MISO-DR-02-012


10/14/2010


10/13/2010

MISO's Motion to Compel Responsive Information from Duke Energy


10/11/2010

MISO Notice of Filing Certification


10/5/2010

MISO's Response to Duke Energy's 092210 Data Requests


10/4/2010


9/23/2010


9/22/2010


9/15/2010


9/13/2010


9/8/2010


8/13/2010


8/13/2010


8/12/2010


8/12/2010


8/9/2010


8/3/2010


8/3/2010


8/2/2010


8/2/2010


8/2/2010


7/27/2010


7/20/2010


7/20/2010


7/20/2010


7/19/2010


7/6/2010


6/28/2010


6/28/2010


6/24/2010


6/1/2010


5/20/2010