ELECTRONIC APPLICATION OF ATMOS ENERGY CORPORATION FOR PRP RIDER RATES BEGINNING OCTOBER 1, 2023
| Case Filings | |
|---|---|
| Filing | Documents |
|
7/8/2026 2:20:14 PM
Order Entered: 1. Atmos’s July 31, 2023 petition for confidential treatment is granted. 2. The designated material granted confidential treatment by this Order shall not be placed in the public record or made available for public inspection for an indefinite period or until further order of this Commission. 3. Use of the designated material granted confidential treatment by this Order in any Commission proceeding shall comply with 807 KAR 5:001, Section 13(9). 4. If the designated material granted confidential treatment by this Order becomes publicly available or no longer qualifies for confidential treatment, Atmos shall inform the Commission and file with the Commission an unredacted copy of the designated material. 5. If a nonparty to this proceeding requests to inspect the material granted confidential treatment by this Order and the period during which the material has been granted confidential treatment has not expired, Atmos shall have 20 days from receipt of written notice of the request to demonstrate that the material still falls within the exclusions from disclosure requirements established in KRS 61.878. If Atmos is unable to make such demonstration, the requested material shall be made available for inspection. Otherwise, the Commission shall deny the request for inspection. |
|
|
11/3/2023 4:29:22 PM
Order Entered: 1. Atmos’s petition for rehearing is denied in part and granted in part in accordance with the above findings. 2. The September 29, 2023 Order is clarified that the revised PRP spending cap of $30 million applies prospectively. 3. The remainder of the September 29, 2023 Order not in conflict with this Order remains in effect. 4. This matter is closed and removed from the Commission’s docket. |
|
|
10/18/2023 11:58:57 AM
Atmos Energy PRP Petition for Rehearing 2023-00231 Eric Wilen Atmos Energy Corporation |
|
|
9/29/2023 2:48:51 PM
Final Order Entered: 1. The PRP rates proposed by Atmos are denied. 2. The PRP rates in Appendix B to this Order are approved for service rendered by Atmos on and after the date of entry of this Order. 3. Atmos may use the PRP ROE approved in this Order in its next PRP filing without filing ROE testimony. 4. Within 20 days of the date of entry of this Order, Atmos shall file with this Commission, using the Commission’s electronic Tariff Filing System, revised tariff sheets setting out the rates approved herein and reflecting that they were approved pursuant to this Order. 5. This case is closed and removed from the Commission’s docket. |
|
|
7/31/2023 3:16:17 PM
Atmos 2023 KY PRP Filing - Petition for Confidentiality 2023-00231 Eric Wilen Atmos Energy Corporation |
|
|
7/31/2023 3:12:45 PM
Atmos Energy 2023 KY PRP Filing Application 2023-00231 Eric Wilen Atmos Energy Corporation |
|
|
7/11/2023 3:48:57 PM
20230711_PSC Acknowledgment Letter.pdf |
|
|
7/11/2023
Atmos Energy Corporation Notice of Intent to File an Application for PRP Rider Rates beginning October 1, 2023 Using Electronic Filing Procedures |
|