Kentucky Public Service Commission


View Case Filings for: 2025-00351


Case Number:2025-00351
Service Type:Water
Filing Date:11/10/2025
Category:Regular
Utilities:

Warren County Water District


Electronic Case

ELECTRONIC APPLICATION OF WARREN COUNTY DISTRICT FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT THE ALVATON AREA CAPACITY IMPROVEMENT PROJECT PURSUANT TO THE PROVISIONS OF KRS 278.020 AND 807 KAR 5:001









Case Filings
FilingDocuments
1/7/2026 11:53:06 AM

Final Order Entered: 1. Warrant District is granted a CPCN for the proposed project as submitted. 2. Warren District shall obtain approval from the Commission prior to performing any additional construction not expressly authorized by this Order. 3. Warren District shall file with the Commission documentation of the total costs of this project, including the cost of construction and all other capitalized costs (e.g., engineering, legal, and administrative), within 60 days of the date that construction is substantially completed. Construction costs shall be classified into appropriate plant accounts in accordance with the Uniform System of Accounts for water utilities prescribed by the Commission. 4. Warren District shall notify the Commission in writing one week prior to the actual start of construction. 5. Warren District shall require the construction to be inspected under the general supervision of a professional engineer with a Kentucky registration in civil or mechanical engineering to ensure that the construction work is done in accordance with the contract drawings and specifications and in conformance with the best practices of the construction trades involved in the project. 6. Warren District shall immediately notify the Commission upon knowledge of any material changes to the projects, including but not limited to an increase in cost and any significant delays.


12/16/2025 12:48:24 PM

Motion to Submit for Decision


Tina Frederick Warren County Water District

Motion_to_Submit.pdf

Motion to Submit on Written Record

12/5/2025 11:58:01 AM

Warren Districts Response to Staffs First Request


Tina Frederick Warren County Water District

01_Response_Staffs_First_Request.pdf

Warren District's Response to Staff's First Request

11/24/2025 12:03:34 PM

Data Request


11/20/2025 1:16:51 PM

Order Entered: 1. The procedural schedule set forth in the Appendix to this Order shall be followed. 2. Warren District shall respond to all requests for information propounded by Commission Staff, whether identified on the procedural schedule or otherwise, as provided in those requests. 3. Any party filing a paper with the Commission shall file an electronic copy in accordance with the electronic filing procedures set forth in 807 KAR 5:001, Section 8. Electronic documents shall be in portable document format (PDF), shall be searchable, and shall be appropriately bookmarked. The Commission directs the parties to the Commission’s July 22, 2021 Order in Case No. 2020-00085 regarding filings with the Commission.


11/13/2025 9:52:04 AM

20251113_PSC No Deficiency Letter.pdf


11/10/2025 3:39:35 PM

Water Division Application for a CPCN to Construct Alvaton Area Capacity Improvement Project


Tina C Frederick Warren County Water District

Application_CPCN_Alvaton_Capacity_Project_Warren_Water.pdf

Application for a CPCN - Alvaton Capacity Improvement Project

10/22/2025 11:33:57 AM

20251022_PSC Acknowledgment Letter.pdf


10/22/2025 11:31:18 AM

Warren County Water District Notice of Intent to File an Application for a Certificate of Public Convenience and Necessity to Construct the Alvaton Area Capacity Improvement Project Pursuant to the Provisions of KRS 278.020 and 807 KAR 5:001 Using Electron


20251022_Warren County Water District Notice of Intent and Election.pdf

Warren County Water District Notice of Intent and Election