View Case Filings for: 2025-00325


Case Number:2025-00325
Service Type:Water
Filing Date:10/21/2025
Category:Regular
Utilities:

Hyden-Leslie County Water District


Electronic Case

ELECTRONIC APPLICATION OF HYDEN-LESLIE COUNTY WATER DISTRICT FOR A DECLARATORY ORDER THAT THE CONSTRUCTION OF THE CUTSHIN WATER LINE REPLACEMENT PROJECT - PHASE 1 DOES NOT REQUIRE A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY









Case Filings
FilingDocuments
12/23/2025 10:06:01 AM

Final Order Entered: 1. Hyden-Leslie District’s application for a declaratory order is granted. 2. Hyden-Leslie District has adequately demonstrated that it should be exempt from obtaining a CPCN for its proposed Project, as outlined in KRS 278.020(1)(a). 3. Hyden-Leslie District shall notify the Commission of any material revision(s) to the Project within three business days of said revisions and seek a determination if said revision(s) alter the findings herein. 4. This case is closed and removed from the Commission’s docket.


10/21/2025 5:27:21 PM

Application for Declaratory Order


Gerald E. Wuetcher Hyden-Leslie County Water District

Application_ExhibitD_ProjectPlans.pdf

Application - Exhibit D (Project Plans)

Application_ExhibitE_ProjectSpecifications.pdf

Application - Exhibit E (Project Specifications)

Read1st.pdf

Transmittal Letter

10/1/2025 8:56:58 AM

20251001_PSC Acknowledgment Letter.pdf


10/1/2025 8:55:01 AM

Hyden-Leslie County Water District Notice of Intent to File an Application for a Declaratory Order Using Electronic Filing Procedures


20250930_Hyden-Leslie County Water District Notice of Intent and Election.pdf

Hyden-Leslie County Water District Notice of Intent and Election