Kentucky Public Service Commission


View Case Filings for: 2019-00270


Case Number:2019-00270
Service Type:Electric
Filing Date:9/27/2019
Category:Regular
Utilities:

Big Rivers Electric Corporation


Case Nature:

APPLICATION OF BIG RIVERS ELECTRIC CORPORATION FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 161 KV TRANSMISSION LINE, AND A 345 KV TRANSMISSION LINE IN MEADE COUNTY, KENTUCKY









Case Filings
FilingDocuments
11/7/2022 12:02:55 PM

Order Entered: 1. BREC’s motion for confidential treatment is granted. 2. The designated material granted confidential treatment by this Order shall not be placed in the public record or made available for public inspection for an indefinite period until further Order of this Commission. 3. Use of the designated material granted confidential treatment by this Order in any Commission proceeding shall comply with 807 KAR 5:001, Section 13(9). 4. BREC shall inform the Commission if the designated material granted confidential treatment by this Order becomes publicly available or no longer qualifies for confidential treatment. 5. If a nonparty to this proceeding requests to inspect the material granted confidential treatment by this Order and the period during which the material has been granted confidential treatment has not expired, BREC shall have 30 days from receipt of written notice of the request to demonstrate that the material still falls within the exclusions from disclosure requirements established in KRS 61.878. If BREC is unable to make such demonstration, the requested material shall be made available for inspection. Otherwise, the Commission shall deny the request for inspection. 6. The Commission shall not make the requested material available for inspection for 30 days from the date of service of an Order finding that the material no longer qualifies for confidential treatment in order to allow BREC to seek a remedy afforded by law.


3/15/2021 3:50:40 PM

Order Entered: 1. BREC’s motion for confidential treatment is granted.


1/23/2020 2:34:17 PM

Final Order Entered: 1. BREC is granted a CPCN to construct and operate the proposed transmission facilities as set forth in its application. 2. BREC shall file a survey of the final location of the transmission facilities after any modifications are finalized as authorized herein and before construction begins. 3. BREC shall file "as-built" drawings or maps within 60 days of the completion of the construction authorized by this Order. 4. BREC's request for authority to move the substations from the locations shown on the maps filed with the application so long as the substations are not moved onto different property owners is granted. 5. BREC's motion for a deviation regarding the filing of the attachment to its discovery response on electronic format is granted. 6. BREC shall immediately notify the Commission upon knowledge of any material changes to the scope of the transmission projects, including, but not limited to, increase in cost, any significant delays in the construction of the transmission line, or any changes in the route of the transmission line or the location of the substations. 7. Any documents filed pursuant to ordering paragraphs 2, 3, and 6 of this Order shall reference the case number of this matter and shall be retained in the post-case correspondence files. 8. This case is closed and removed from the Commission's docket.


12/9/2019

Big Rivers Electric Corporation Response to Commission Staff Second Request for Information


11/22/2019 11:35:01 AM

Commission Staff's Second Request for Information to Big Rivers Electric Corporation


11/14/2019

Big Rivers Electric Corporation Response to Commission Staff First Request for Information and Motion for Deviation


11/14/2019

Big Rivers Electric Corporation Response to Commission Staff First Request for Information and Motion for Deviation


11/14/2019

Big Rivers Electric Corporation Response to Commission Staff First Request for Information and Motion for Deviation


11/4/2019 10:33:29 AM

Commission Staff's First Request for Information to Big Rivers Electric Corporation


10/8/2019 3:33:47 PM

Order Entered: 1. The time in which the Commission must issue its decision in this case is extended to 120 days. 2. The procedural schedule set forth in the Appendix to this Order shall be followed in this proceeding. 3. a. Responses to requests for information in paper medium shall be appropriately bound, tabbed, and indexed. Responses that are required to be provided on electronic medium shall be in portable document format (PDF), shall be searchable, and shall be appropriately bookmarked. b. Each response shall include the name of the witness responsible for responding to the questions related to the information provided. Each response shall be answered under oath, or for representatives of a public or private corporation or a partnership or an association or a governmental agency, be accompanied by a signed certification of the preparer or person supervising the preparation of the response on behalf of the entity that the response is true and accurate to the best of that person's knowledge, information, and belief formed after a reasonable inquiry. c. Any party shall make timely amendment to any prior response if it obtains information which indicates that the response was incorrect when made or, though correct when made, is now incorrect in any material respect.


10/1/2019 9:15:02 AM

No deficiency letter


9/27/2019 4:39:11 PM

Acknowledge Receipt of Filing


9/27/2019

Big Rivers Electric Corporation Application for a Certificate of Public Convenience and Necessity to Construct a 161 KV Transmission Line, and a 345 KV Transmission Line in Meade County, Kentucky


7/31/2019 4:49:58 PM

Acknowledge Receipt of Filing


7/31/2019

Big Rivers Electric Corporation Notice of Intent to File an Application for a Certificate of Public Convenience and Necessity to Construct a 161 KV Transmission Line, and a 345 KV Transmission Line in Meade County, Kentucky