Kentucky Public Service Commission


View Case Filings for: 2014-00257


Case Number:2014-00257
Service Type:Gas
Filing Date:8/15/2014
Category:Regular
Utilities:

Natural Gas of Kentucky, Inc.


Case Nature:

APPLICATION OF NATURAL GAS OF KENTUCKY FOR APPROVAL OF CONSTRUCTION OF AN INTRASTATE NATURAL GAS PIPELINE, ISSUANCE OF A CERTIFICATE OF CONVENIENCE AND NECESSITY AND APPROVAL OF FINANCING









Case Filings
FilingDocuments
1/20/2015 1:50:53 PM

Order entered: NGK's petition for confidential protection is hereby granted.


10/2/2014 11:09:55 AM

Order Entered: (1) Natural Gas is granted a CPCN for construction of the Project set forth in the application. (2)The Transportation Agreement between Natural Gas and Scotty's is reasonable and is approved. (3) Natural Gas shall, no later than 90 days after the completion of the project, file with the Commission a statement of the actual costs of the construction. (4) Natural Gas shall file a copy of the "as-built" drawings and a certified statement from the engineer that the construction has been satisfactorily completed in accordance with the contract plans and specifications within 60 days of substantial completion of the construction certified herein. (5) Natural Gas shall require the construction to be inspected under the general supervision of a professional engineer licensed to practice in the Commonwealth of Kentucky in civil or mechanical engineering to ensure that the construction work is done in accordance with the contract drawings and specifications and in conformance with the best practices of the construction trades involved in the project. (6) Natural Gas shall notify the Commission one week prior to the actual start of construction and at the 50 percent completion point. (7) Natural Gas shall not incur any long-term indebtedness associated with this project without applying to the Commission for approval pursuant to KRS 278.300.


9/17/2014

Natural Gas of Kentucky, Inc. Response to Staff's Request at 9/10/2014 Conference


9/15/2014 3:21:24 PM

Memorandum dated 9/12/2014 for Informal Conference of 9/10/2014; Comments, if any, due within five days of receipt


9/9/2014 2:51:35 PM

Commission Staff's Notice of Informal Conference


8/20/2014 3:20:53 PM

Deficiency cured letter


8/15/2014

Natural Gas of Kentucky Inc. Response to PSC Letter of 07-25-14 (disc and maps included)


7/25/2014 10:37:33 AM

Deficiency letter


7/18/2014 3:14:25 PM

Acknowledge Receipt of Filing


7/18/2014

Application of Natural Gas of Kentucky for Approval of Construction of an Intrastate Natural Gas Pipeline, Issuance of a certificate of Convenience and Necessity and Approval of Financing


7/18/2014

Application of Natural Gas of Kentucky for Approval of Construction of an Intrastate Natural Gas Pipeline, Issuance of a certificate of Convenience and Necessity and Approval of Financing